SWELL cavity - planning - 2023.2
Participants:
M. Therass, L. Ferreirra, C. Pereirra, G. Bellini, S. Leith, G. Rosaz, F. Sanda, M. Timmins
Summary
Mathieu explained that helicoils inserts are missing into the SWELL quadrants preventing him to mount the toolings.
The main-workshop has been notified and will take action next week.
He also mentioned that the tie rods had to be remachined due to defective threads.
Guillaume showed a first draft of a planning (here after). It shows how tight the schedule will be to deliver the cavity by may.
Guillaume said that he will provide soon a more detailed and accurate version of that planning.
Leonel asked which of the 400MHz baseline cavity and SWELL 1.3GHz should be considered as a priority in case of planning conflicts regarding surface treatments.
Guillaume acknowledged the remark and stated he would raise the question to the management to obtain a common agreement on that point.
The transport boxes job was released by F. Zimmerman and signature is now pending at M. Benedikt.
Jan | Feb | Mar | Apr | May | ||||||||||||||||
RF blank assembly | ||||||||||||||||||||
Coating blank assembly | ||||||||||||||||||||
Nb tooling degreasing | ||||||||||||||||||||
EP tooling degreasing | ||||||||||||||||||||
RF tooling degreasing | ||||||||||||||||||||
quadrant degreasing | Q1-Q2-Q3-Q4 | |||||||||||||||||||
quadrant EP | Q1 | Q2 | Q3 | Q4 | ||||||||||||||||
quadrant LPWR | Q1 | Q2 | Q3 | Q4 | ||||||||||||||||
quadrant coating | Q1 | Q2 | Q3 | Q4 | ||||||||||||||||
quadrant LPWR2 |