Skip to main content

WP6 coordination meeting #4

Europe/Zurich
CERN

CERN

General (Claudia)

  • Please check open actions under the JIRA WP6 board: WP6 - RP & Safety - Agile Board - CERN Central Jira
  • For any actions under your responsibility, please let me know if you have any updates
  • In case of any changes to the board, don’t hesitate to contact me

 

Safety (Melania not present)

 

RP (Claudia)

  • FLUKA model to be updated with WP8 once SHiP provided input on muon shield
  • BDF
    • Olin has performed soil activation studies for NA62 and various BDF shielding configurations. Once discussed with Claudia, a meeting will be scheduled with Pavol. The preliminary irradiation station shielding might be affected by it
    • Olin has performed further studies for the service cell to increase statistics and reduce the roof shielding thickness. Action/Claudia to investigate dose rate limit to be applied on roof
    • Action/Olin to perform activation studies downstream of BDF once muon shield has been updated
    • Action/James to potentially work on BDF FLUKA model improvement and fluence spectra scoring for radioactive transport and waste considerations. A target diameter of 25 cm to be used as causing highest activity concentrations. Ta cladding to be included
    • Elzbieta has performed further TCC8 dismantling studies for the target station and the TAX, separating the items according to drawings from Nicolas. Action/Ela to put fluences to CERNBOX once available. Ela also added new cooling time for July 2028 to the inventory list
    • Angelito informed that excavations for TT7 shielding recovery will start on 19/05. For the moment, no place for the shielding blocks cleaning and painting has been identified. Action/Claudia to check with Francois to urgently identify a place.
    • Target material for prototype tests not ready in time requiring a delay of the installation after the TS. Yann investigated dose rates of PMIs and proposes a 16 h cool-down and a dose rate on the PMI next to the setup of < 2 mSv/h. Action/Yann to write an email to the relevant person
    • NA62 dismantling inventory list has been provided. Action/Yann/Renaud to provide information on radioactive waste zoning

 

RP transport/waste (Philippe/Luca/Fred)

  • Transport container dimensions for the TCC8 dismantling were provided by Philippe
  • LS3 waste forecast for HI-ECN3 should be ok

 

FIRIA (Rahul, Oriol)

  • See slides about relevant updates

 

Access & Safety Systems (Boris)

  • An access system was not yet foreseen for the BDF partition. Action/Boris current WP4 plans and requirements from RP/FIRIA/Safey to be collected
  • Boris informed about an upcoming change in the sub-WP management. Details to be transmitted once known

 

Occupational health (Jamie)

  • See slides about relevant updates
  • The funding for the new tent has not been approved. Alternatives are being investigated. Main constraint during LS3 comes from the NA62 dismantling
There are minutes attached to this event. Show them.
    • 15:00 15:05
      News 5m
      • JIRA: https://its.cern.ch/jira/secure/RapidBoard.jspa?rapidView=9179&projectKey=RPWG&view=detail&selectedIssue=RPWG-24#
      Speaker: Claudia Ahdida
    • 15:05 16:00
      Round table sub-worpackages 55m
      Speakers: Boris Morand (CERN), Claudia Ahdida, James John Scott Currie, Melania Averna (CERN), Mr Oriol Rios (CERN), Philippe Bertreix (CERN), Rahul Kallada Janardhan (HSE-OHS), Mr Renaud Charousset (CERN)
      • Safety 10m
        Speaker: Melania Averna (CERN)
      • RP 10m
        • WP6/8 FLUKA model
        • BDF
          -- Soil activation (NA62 vs BDF different configs)
          -- Irradiation station shielding
          -- Service building (better statistics, shielding thickness roof)
          -- Activation risks in downstream BDF
          -- BDF W target activation and container (Diam. 25 cm) and update of model
          -- He circuit RP risks
        • TCC8 dismantling
        • TT7 shielding recovery
        • NA62 dismantling
        • Prototype target tests
        • FIRIA studies (MHS coil)
        Speaker: Claudia Ahdida
      • Radioactive Transport & Waste Management 10m

        Regarding the transports packages, please find information below :
        - Type A truck x int dim (Lwh) : 4880 x 1640 x 2545 mm. Max weight material : 3700 kg
        - IP2 cargo box x int dim (Lwh) : 9764 x 1400 x 2280 mm. Max weight material : 30650 kg
        - TYPE A ISO 20ft x int dim (Lwh) : 5901x 2350x 2331mm. Max weight material : 20600kg

        Speakers: Frederic Lionel Aberle (CERN), Philippe Bertreix (CERN)
      • FIRIA 10m
        Speaker: Rahul Kallada Janardhan (HSE-OHS)
      • Access & Safety Systems 10m
        Speaker: Boris Morand (CERN)