HL-LHC BGI - magnet design update

Europe/Zurich
865/2-C19 (CERN)

865/2-C19

CERN

10
Show room on map
Chiara Pasquino (CERN), Gunn Khatri (CERN), James Storey (CERN)
Zoom Meeting ID
65961147691
Host
Gunn Khatri
Useful links
Join via phone
Zoom URL

draft !

Present:

William, Dominique, Lauren, Gunn

Discussion

  • Introduction & Presentation

    • Dominique presented an overview of the BGI project and its magnet requirements.
    • The latest design and integration model for LHC Point 4, developed in CATIA by František, was shown.
  • Main Magnet Design

    • The new main magnet design has been optimized to be compatible with the existing power converters from the BBLR instrument (600A, 40V) and new DC cables.
    • The magnet and cable require 24V @ 490A, leaving a sufficient margin.
  • Recycling of MDX Magnets

    • The old MDX magnets will be repurposed as trim magnets, using existing power converters and cables (125A, 125V).
    • The magnet and cable require 37V @ 45A, also leaving a margin.
  • Magnet Design & Field Quality

    • The design has been fine-tuned for cost optimization by reusing existing power converters, achieving the best possible outcome.
    • The coil is circular, with tapered and rounded yoke ends to maximize field homogeneity (dB/B < 1E-3).
    • Magnetic field harmonic numbers were presented, requiring approval from the LHC beam optics team (BE-ABP, Riccardo?).
    • In particular, B3 harmonics appear relatively high, but their impact on the LHC beam is expected to be negligible.
  • Cost & Timeline

    • Preliminary cost estimates and procurement timeline were discussed (figures not yet finalized).
    • If the magnet design is approved by BE-ABP, the production plan will be:
      1. Manufacturing of one pre-series magnet.
      2. Followed by production of three additional magnets.
    • No spare magnet will be built; only spare coils will be ordered.

 

Action Items

  1. EPC & BBLR Team

    • Officially reserve the four existing power converters from BBLR.
  2. LHC Beam Optics Team (BE-ABP)

    • Verify that the field harmonics of the new magnet meet LHC beam requirements.
  3. BI-ML Team

    • Obtain the 3D model from František.
    • Begin working on the BGI instrument integration and support mechanics.
  4. Machine Protection Team (Jan Uthoven)

    • Update them on the latest magnet design.
  5. V-IPM Simulations

    • Run simulations using the latest B-field map.
There are minutes attached to this event. Show them.