4th Interaction region design meeting
Meeting Minutes – Injection Region Design
Date: 11/07/2025
Participants: Patric, Jim, Justin, Daniel, Marlene
Next Meeting: 31/07/2025
1. EDMS & Documentation
-
EDMS link for sharing drawings (https://edms.cern.ch/ui/#!master/navigator/project?P:1002757716:101807714:subDocs) is functional and in use.
2. Upstream Pipe and Sextupole Interference
-
Despite adding the extension pipe upstream of the injection dipole, a clear aperture conflict remains (radius 7.5 cm, Ø135 mm pipe) with the sextupole.
-
Action: Eleonora and Marlene to consult P. Schwarz regarding the possibility of removing (shaving off) 2.5 cm from the sextupole.
- Could consider making the vapor source narrower?
3. Expansion Volume in Beamline
-
Estimated space requirement: 30 cm (to be confirmed via thermal simulations).
-
Apertures: Two apertures are preferred. No modifications expected post-installation; aperture plate can be thick.
-
Shutters: May be needed. Number of operational cycles to be defined.
-
Action: Eleonora, Marlene to send the electron beam envelope to Jim.
-
Note: The gap in this region is very small (~30 cm).
- Action: Jim, Eleonora, Marlene check the distance between the last magnet and the focus.
4. Corrector + BPM Integration
-
Concern: Does the corrector + BPM assembly fit within the available 250 mm space, including vacuum connection interfaces?
-
Action: Integration check required to ensure compatibility.
- Action: Eleonora, Marlene to confirm with BI if possible
5. Plasma Extension Region
-
Current distance between the two plasma cells: ~3.349 m.
- This distance was/is already in the CAD sent to GWA by Nicolas, so no change wrt that CAD
-
Action: Marlene to discuss feasibility with Edu and present an update at the next CSCP meeting.
6. MPP Machine Shop Support
-
Discussion: Identify which components can be fabricated by the MPP Machine Shop.
-
Note: A possible visit to GWA in Munich was mentioned.