WLCG Sustainability Forum Meeting #9: Environmental sustainability metrics relevant to sites

→ Europe/Zurich
Zoom only

Zoom only

Caterina Doglioni (The University of Manchester (GB)), David Britton (University of Glasgow (GB)), Domenico Giordano (CERN)
Description

In this meeting, we will discuss which quantities are relevant for environmental sustainability for WLCG sites, and how to define them -  starting from PUE. The detailed agenda will be shared closer to the date. 

If you would like to give input to this topic in advance of this meeting, please email wlcg-sustainability-forum-coordination@cern.ch. 

Zoom Meeting ID
68108210654
Host
Caterina Doglioni
Useful links
Join via phone
Zoom URL

WLCG environmental sustainability forum

 

Notes were obtained using Zoom AI on CERN servers by asking targeted questions in the Zoom AI window after each talk.

 

Alex Owen - Thoughts on PUE and QMUL heat recovery

 

Alex Owens talk focused on the limitations of PUE as a metric and what alternatives might better capture a data center's environmental footprint.

PUE: What It Is and Its Problems

  • PUE = total facility energy / IT equipment energy.
  • Key weaknesses: it rewards inefficiency (PUE worsens as IT load drops), ignores useful work as it includes idle, cannot easily reflect renewable energy use, ignores heat recovery, and ignores water usage.
  • PUE is not a constant as it varies day to day and very likely seasonally.

Queen Mary's Data Center Setup

  • A recently refurbished data center uses in-row chillers, heat pumps, district heating system, with a design PUE of 1.3.
  • Metering exists at multiple levels: facility (M1, M2), rack (PDUs), server (IPMI/BMC), and CPU (RAPL counters).
  • PDU readings are a good proxy but still don't capture the full picture compared to electricity meter readings.

Heat Recovery Results

  • Over 3 months, more than 57.5% of recovered heat was reused into the district heating system.
  • Heat recovery is not captured by PUE at all.

Alternative Metrics Proposed

  • Energy Reuse Factor (ERF): reused energy * total facility energy (a simple 0-1 ratio)
  • Carbon Usage Effectiveness (CUE): total carbon footprint * IT energy. However, contracts are not reflected in the “local” energy being used from the grid where the data center is.
  • Carbon-Free Energy Score (Google's metric): used to match hourly carbon intensity against purchased carbon-free energy.

Key Conclusions

  • For total facility energy, monthly energy usage figures are preferable to IPMI * PUE estimates.
  • Sites with on-site solar/wind or heat recovery should report both ERF and carbon-free energy scores.
  • Alex also floated an "Extended PUE" concept that could account for IPMI undercounting, on-site renewables, and heat reuse, although this remains a speculative idea.

 

Jarek Polok - CERN data centers and how to measure PUE

 

Jarek from CERN presented PUE data for CERN's data centers, noting that the worldwide average PUE is currently 1.52, down from 1.65 three years ago.

 

CERN's Data Centers:

  • The old data center (Meyrin/MDC) averages a PUE of 1.45.
  • The newer data center (Prevessin/PDC), operating for about 2 years, achieves 1.13, and a very small data center (Network Hub) reaches 1.10 due to efficient cooling.

How Data Is Collected:

  • The old center uses electrical department measurement systems on main power points, injecting data via a CERN-wide data interchange protocol.
  • The PDC uses a contractor-provided monitoring system, read via REST API every 90 seconds, with data presented in Grafana dashboards.
  • PDU-level errors range from 2-5%, and IPMI errors can reach 15-20%, making them less suitable for precise measurements compared to industrial systems (< 1% error).
  • PUE values vary more with older cooling system at MDC than at PDC / Hub
    • PDC stays relatively flat over 12 months, while the old center shows significant variation due to an aging cooling system that needs modernization in the next ~5 years.

Scale & Energy Source:

  • Total energy consumption is close to 6 MWh, with PDC at 2.3 MWh and Meyrin at 3.5 MWh.
  • CERN benefits from the French electrical grid: over 60% of energy comes from nuclear power, with only 10% from fossil fuels.

Jarek also noted that the PDC's good PUE comes at the cost of higher water usage, especially during hot summers.

 

Luciano Scarponi - INFN CNAF data center (Tier-1 in Bologna)

 

lbscarponi presented the INFN CNAF Data Center Tier 1 in Bologna, housed in a renovated building (a former tobacco factory).

 

Facility Overview

  • The data center is designed to host up to 3 MW of IT systems, divided into five areas including a high-density area (racks up to 50 kW each) and an expansion area.
  • Cooling uses two water systems: chilled water (19C/26C inlet/outlet) and warm water for direct liquid cooling, used by the Leonardo supercomputer.

PUE Performance

  • Current instantaneous PUE is approximately 1.345.
  • In 2025, the annual average PUE was 1.45, rising to 1.6-1.7 in summer months.
  • PUE variation is driven almost entirely by external temperature: in cold months (October-April), the chiller shuts off and only the adiabatic system runs.
  • 2026 saw a very hot and extended summer, worsening PUE compared to 2025.

Other Metrics

  • Energy Reuse Factor: The data center is heating an adjacent building but is not yet monitoring the reuse system. Infrastructure for district heating is in place but has no users yet.
  • Water Usage Effectiveness (WUE): Reported at 0.21 for 2025; rainwater recovery is also used.
  • Renewable Energy: The electricity provider supplies only certified renewable energy, though the speaker acknowledged this could be considered "greenwashing."

 

IT load has remained stable since April 2025, confirming that PUE changes are cooling-driven rather than workload-driven.

 

Discussion:

 

(1) What should we record?

 

Domenico's question/statements

  • Domenico acknowledged that PUE was a reasonable starting point 3-5 years ago for approximating WLCG's environmental impact, but argued it is time to move forward.
  • Domenico suggested that rather than collecting a single static PUE value, the community should aim to collect richer, more granular energy data, ideally monthly absolute energy figures from sites and sub-sites.
  • Domenico proposed adding the Energy Reuse Factor to CRIC alongside PUE, noting it would be irrelevant for many sites but would highlight those making progress on heat recovery.

 

David's response

  • David agreed that PUE was never intended to be a precise calculation tool, but rather to encourage sites to think about efficiency.
  • David noted that PUE is a variable, not a constant. This is something not fully appreciated when it was first adopted.
  • David pointed out that the new accounting system under development could, in principle, attach a per-job PUE value if sites can provide instantaneous estimates, though a monthly average is a more realistic near-term goal.
  • David agreed that the Energy Reuse Factor and carbon content of input power are the two additional dimensions worth capturing, suggesting a simple survey of sites asking who reuses energy and who has local green power as a practical first step.

 

Shared Conclusion Both agreed the pragmatic path forward is to continue reporting PUE in CRIC, add the Energy Reuse Factor, and work toward monthly energy reporting from sites.

 

(2) Connections with metrics in ENSURE

 

Caterina's update on ENSURE

  • Caterina provided an update on the ENSURE project, which had surveyed a few sites from WLCG to determine what is possible for them to measure
  • Caterina distinguished between basic KPIs to be filled (such as IT energy) and derived KPIs (such as PUE, CUE, WUE), arguing it is preferable to collect basic metrics rather than derived ones, since the basic figures are needed as inputs for multiple metrics.
  • Key items recommended for collection include: cooling information, renewable energy consumed, energy reused outside the facility, and water input, as well as a simple yes/no on hardware inventory.
  • Caterina noted this approach is compatible with existing standards and regulations, and stressed it should be a two-way discussion rather than an imposition on WLCG.


David's Response

  • David raised a practical concern: with 170 sites, the harder the data collection process, the less engagement WLCG will realistically get.
  • David also flagged a sensitive issue: historically, WLCG avoided asking directly about energy from data centers because some sites do not monitor their electricity, and raising the question risks drawing attention to significant unaccounted costs at smaller institutes.

Shared Direction Both broadly aligned on the need to collect basic energy quantities rather than just derived metrics, while acknowledging the practical constraints of engaging a large and varied set of sites.

 

(3) PUE: granularity and interpretation

 

Pepe Flix Molina offered the following observations during the discussion:

On PUE as a dynamic value

  • Pepe agreed with Domenico that PUE is a dynamic value, not a static one, noting that sites using free cooling at night can see large variation, especially in winter between night and day, as well as seasonal differences.

On granularity of data collection

  • Pepe acknowledged that a very fine-grained system might be problematic, but suggested that since many sites are already collecting time-series data, it could be feasible to collect PUE as a time series for sites that already do this.
  • For large Tier-1 sites with monthly reports, Pepe proposed collecting the average monthly PUE value as part of the existing monthly accounting process.

On interpreting PUE trends with increasing loads

  • Jose raised a concern about using PUE to assess whether sites are improving their facilities: as more IT resources are installed for HL-LHC, PUE values will naturally decrease not necessarily because facilities are improving, but simply because more IT load is in the denominator.
  • This means it could become difficult to distinguish genuine facility improvements from PUE reductions caused by increased IT power. So at minimum, the community needs to be aware of this limitation when interpreting PUE evolution over time.

 

(4) Views from AUDITOR / Freiburg Tier-2 site and follow-ups from survey

 

Michael:

  • Michael noted he was wearing two hats: developing the accounting tool (technically capable of collecting rich data) and serving as admin of a smaller Tier-2 site.
  • At the smaller site, the compute center is operated by central IT, meaning it took roughly half a year to a year just to obtain a single PUE value with no prospect of time-series measurements.
  • Michael therefore supported having two parallel approaches: a single fallback number for sites that cannot provide more, alongside precise measurements for sites that can.

Domenico:

  • Domenico suggested preparing a survey for sites to understand their power management capabilities, asking whether they are in a situation like Alex's (with granular metering) or like Michael's (relying on a single static number).
  • Domenico also raised the concern that sites may have difficulty exposing absolute energy values, since those figures, multiplied by electricity cost or country CO2 intensity, directly reveal spending and emissions - this is a potentially sensitive disclosure.

Pepe:

  • Pepe confirmed there is a survey being prepared already has a section on PUE asking whether sites can measure it and what difficulties they face.
  • Pepe acknowledged that water use effectiveness and energy reuse metrics are not yet included in the survey, and suggested these could be added.
  • David agreed this would be valuable and noted he had not yet reviewed the survey questions, asking Pepe for a target send-out date.
  • Pepe confirmed the survey is being finalised with Nadir from Rome, incorporating all feedback received, and that there is still time to add further questions.
    • TODO: Caterina should also check against ENSURE survey (more limited, but deeper) to make sure we align on the core measurements

 

(5) Further discussions on granularity

 

David:

  • David noted that WLCG's main accounting already relies on rough approximations (e.g., average HEP score per site), so imperfect estimates of environmental parameters are still worthwhile, perfection should not be the enemy of progress.

Alex:

  • Alex welcomed hearing other sites' perspectives and found it reassuring that monthly PUE variation is not unique to QMUL
  • Alex suggested per-month granularity fits naturally, since some accounting already happens monthly, and rolling environmental data into existing monthly accounting makes practical sense.
  • Alex recommended approaching sustainability teams rather than Estates departments, finding them more responsive particularly given increasing mandated carbon reporting requirements across Europe and beyond.

Pepe:

  • Pepe highlighted that in Spain, CO2‚ emissions vary by a factor of two between daytime and nighttime, meaning the carbon impact of running jobs fluctuates significantly.
  • Pepe noted that PUE differences between night/day and summer/winter compound this effect, and that averaging hides the real environmental impact.
  • Pepe argued that sites are increasingly building real-time or hourly monitoring of kg CO2‚ emitted, and that this level of time-series granularity is ultimately needed to understand true facility impact.

David:

  • David agreed with Pepe that time-series data is important.

Alex:

  • Alex concurred that time-series data matters, adding that back-calculating metrics at month-end for all jobs completed that month may be more practical than calculating per job as it finishes.

Jose:

  • Jose noted that the per-job CO2 accounting is very complex in practice: a machine consuming, say, 500 watts hosts multiple job slots, and simply dividing power by slot count does not capture whether a job was CPU-intensive or I/O-intensive.
  • Jose concluded that sharing machine power across job slots is the only feasible approach, while acknowledging this leaves important distinctions unaccounted for.

Alex/Domenico:

  • Alex/Domenico observed this reinforces David's earlier point: the goal should be "good enough, not perfect."

 

 

(6) Final remarks

 

Domenico:

 

On GPU Power and PUE Paradox

  • Domenico noted that GPU power consumption will increasingly dominate cooling requirements more than CPU-based workloads.
  • This creates a paradox: consuming more power (due to GPUs) could paradoxically result in a lower (better-looking) PUE, since the IT load in the denominator grows a distortion that must be considered in the long term.

On the Responsibility to Demonstrate Sustainability

  • Domenico argued that the community has the competencies and infrastructure to collect the necessary information.
  • Domenico endorsed Alex's observation that the world is changing: whereas in the past there was concern that countries would not want to expose energy measurements, the situation has reversed — there is now a responsibility to prove that science is sustainable, particularly in response to voices challenging the community's environmental credentials.
  • Domenico expressed that this responsibility is shared by, and in the interest of, many countries, at least across Europe.

 

Pepe:

 

Upcoming Regulation

  • Regulation of data centers may not be far off, as countries grow increasingly aware of data center energy consumption.
  • Data centers could be forced by law to adopt measurement regulations, or energy use could be limited during peak national demand hours.
  • The community needs to proactively propose ways to reduce its energy footprint in anticipation of such requirements.
  • While agreeing WLCG takes this seriously, Pepe flagged a concern: if data is made publicly available and regulations arrive, if individual sites or regions could be penalised for having their data exposed needs to be considered.

 

Caterina brings up the question (which will be emailed): data centers > 500 kW (not MW!) are mandated by regulation to record fairly granular (non-derived) data according to Regulation 2024/1364 being updated this month

 

Dave:

 

David's Final Point:  Default PUE Value for CRIC

David shared data on global average annual PUE trends over the past ~8 years, noting that the worldwide average has not been decreasing linearly.

  • David highlighted that the figure of 1.52 cited earlier by Jarek is a straight average, not weighted by data center size.
  • When weighted by size, the true average drops to 1.36.
  • However, David observed that roughly 95% of WLCG's ~170 sites are 15-20 years old, meaning the WLCG average PUE is likely worse than current global figures.
  • Accounting for newer sites like Prevessin (CERN) and Queen Mary, the picture is slightly better, but WLCG's average is still probably worse than published norms.

David's Proposal

  • Based on this, David suggested that a sensible default PUE to enter into CRIC as a starting point would be somewhere between 1.5 and 1.6, leaning closer to 1.6.

Reactions

  • Alex suggested using the 8-year-old value as the default for two years, then switching to the 10-year-old value a deliberately lagged approach to incentivise sites to report their own numbers.
  • Domenico agreed, advocating for the most pessimistic value (e.g., 1.67 from 2019) to push sites to actively measure and declare their real PUE rather than accept a comfortable default.
  • David noted the 2019 spike to 1.67 may have been a COVID-era survey artefact with fewer participating sites.

 

[the end needs to be drawn from the transcript]

There are minutes attached to this event. Show them.
    • 15:30 → 15:40
      Introduction: What WLCG needs 10m
      Speaker: David Britton (University of Glasgow (GB))
    • 15:40 → 15:55
      Thoughts on PUE from QMUL studies 15m
      Speaker: Alex Owen (University of London (GB))
    • 15:55 → 16:05
      What is measured at CERN DCs 10m
      Speaker: Jarek Polok (CERN)
    • 16:05 → 16:15
      INFN approach to PUE measurements 10m
      Speaker: Luigi Benedetto Scarponi
    • 16:15 → 16:30
      Discussion 15m