- Open for ideas on BOND logo
- Jose presented the FE results on the new pole design. Results are almost the same of the original pole. Nico P. already implemented this change.
- Vendela is compiling the results on the new yoke geometry. To be presented in one of next meetings.
- Nico L. presented the results on the DIC measurements. Everything is consistent with our previous measurements and expected behavior.
Racetrack coil mock-up:
- Racetrack wound completely this morning.
- The mock-up will be ready for installation on DIC system on Friday
- We already checked with the guys from the oven. Also if we could adjust manually the plateaus if needed (It can be done but needs to be there in person).
- For the pole constraints, we will link each of the poles to the baseplate trying to simulate the flared end configuration.
- Simon Hopkins provided feedback on the reaction heat treatment to be used (conductor is RRP low-grade)
-
- We will go for a standard MQXF cycle.
CAD update:
- Poles pinned together as one entity (Ti pins).
- Filler in the aperture will not be screwed. It will be "free" and machined to have a good contact with the pole.
- Nico P. to prepare a list on the pole holes.
- Drawings (coil - winding - reaction) for the end of the month.
- Then 1 month for the impregnation drawings (end of July)
- We need to speed-up the missing simulations to finish the structure before Matthieu's final date (end of July)