Installation sequence discussed
- Emptying of the existing TCC4 racks
- Shipment of the empty racks to the UK
- Reinstallation of the racks in TCC4 (rack gallery)
- Installation of the racks in TCV4
- Cabling between TCC4 and TCV4 racks by EN-EL
Installation duration
- 11 weeks foreseen for installation ok, including:
6. Installation of supports
7. Installation and connection of the vapor source
- After that, testing of control system
Points to keep in mind
- Hole drilling for the supports is foreseen for 27 February.
- The injection region dipole magnet should be installed on the CERN alignment system, as indicated in the e-beamline drawing.
- Action (Jim): add this to the CAD.
- Feedback to Tobias: the 11-week installation block is acceptable.
- Action (Justin): share the document on the previous installation sequence.
- Action (Marlene): start preparing the next installation sequence.
Planning
- Justin shared the plan up to the end of June.
- Agreement on this timeline.
Diagnostics for the test chamber
Marlene will share the list of diagnostics for the test chamber, including:
- Wire scanner
- Waist screen
- 2 × alignment screens
- Cavity BPM
- Beam Arrival Monitor
- OSR
- EOS
- ICT
Other points
- Update needed on heat load and electrical infrastructure --> Action: Marlene to follow up
- Action (Marlene): set up a weekly meeting.
- In-person review at CERN: 30 April