PS-BGI Operational Readiness

Europe/Zurich
Description

Quick chat to figure out the final details for the PS-BGI instruments

Zoom Meeting ID
64202946623
Host
Hampus Sandberg
Useful links
Join via phone
Zoom URL

Agenda

Schedule

https://asm.cern.ch/schedules/calendar?type=CPS%20Beam%20commissioning&schedule=CPS%20Beam%20Commissioning%202021&version=1.0&state=Draft&view=month

  • First beam: March 1
  • BPM commissioning: March 3 - 4
  • BGI magnet H/V orbit closure: March 5
  • BGI setup: March 5 - March 10
  • SEMGrid multiturn + BGI test: March 11

Important note: For the BGI setup we need beam in the PS + the BGI magnets at their nominal working point

Instrument hardware

  • NOTE: BGIH magnet has been running at ~80 A last couple of weeks, 176 A is the nominal. Check before first beam (OP)
    • Both BGIH and BGIV magnets have been tested. BGIH working at DC, BGIV pulsing ok 
  • Replacing HV crate at PR.BGI84 (New crate ready to be installed ~Feb. 22) (BGI team)
    • Notified about impact and access next week at the same time as other accesses

Instrument setup

BGI magnet orbit correction (Matt, Alex)

  • BGIH - use correction parameters from 2018
    • Expect no major difference in these parameters caused by the renovated main magnets in the PS during LS2
  • BGIV - find parameters as soon as BPMs are working

Gas injection

  • Ar gas bottles missing in tunnel, issue with order. New urgent delivery requested.
  • Verify that the system is working, i.e. that it injects gas without disturbing the PS and the beam (OP)
    • Check with Jose March 23 how to use the gas injection system
  • Check gas ionisation rate change inside the BGI with gas injection -> Requires beam (Hampus)

Calibration of timing (Hampus)

  • Check and calibrate timing as soon as first beam passes through the BGI instrument
    • PIX.WRF should have a stable phase for a given beam derived from the PSB
    • PPM property "delayFromRFwarningToFirstTurn_rfclock" is used to compensate for delay to first turn at the BGI + cable delays

BGI setup (Hampus)

  • Verify the functionality of the instruments: beam -> gas ionisation -> magnet/HV -> detector -> readout -> profile
  • Adjust instrument settings until we get a good profile