Technical meeting #8 - TE-VSC contribution to the WP5
CERN
-
- 09:00 → 09:10
- 09:10 → 09:15
- 09:15 → 09:25
- 09:25 → 09:35
-
09:35
→
09:45
Discussion 10m
-
09:45
→
10:10
Overview of LS2 Acceptance tests and Lessons Learnt 25m
MoGr Blocks, BPMs, TCPPM, TCSPM and TCLD
Needed Resources
Problems encounteredSpeakers: Giuseppe Bregliozzi (CERN), Gregory Cattenoz (CERN) -
10:10
→
10:25
Overview of LS2 Tunnel Activities and Lessons Learnt 15m
LS2 activities and works done in the tunnel:
Criticality and Problems encountered
Planning and standard activity
Needed ResourcesSpeaker: Eric Page (CERN) -
10:25
→
10:40
Coffee Break 15m
-
10:40
→
11:10
Overview of TE-VSC Contribution to WP#5 30m
Layout: Where and when
Planning & Main milestone
Engineering design & Technical points
Procurements and production overview
Acceptance test definition
Budget & manpower
Urgent actions & Critical pointsSpeaker: Gregory Cattenoz (CERN) -
11:10
→
11:30
History of changes and layout needs 20m
Design overview of the TAXN-D2 Area
Baseline evolution
Integration problems and solution adopted
FRAS
Remote intervention strategySpeaker: Jan Hansen (CERN) -
11:30
→
11:40
Discussion 10m
-
14:00
→
14:15
Remote tooling development 15m
Design & Prototyping
Urgent actions & Critical points
AOBSpeakers: Jan Hansen (CERN), Jonathan Pascal Meignan (CERN) -
14:15
→
14:35
Overview of TE-VSC Contribution to WP#5: Control, cabling & SCADA 20m
Overview of ICM activity
Instrumentation layout
Cabling & racks needs
vacDB & SCADA Integration planning
Procurements & resources
Urgent actions & Critical points
Main milestone
AOBSpeaker: Nikolaos Chatzigeorgiou (CERN) -
14:35
→
14:50
Overview of TE-VSC Contribution to WP#5: Chemical cleaning, coatings, etc.. 15m
Main activities for Cleaning and coating
Main milestone
Procurements & resources
Urgent actions & Critical points
AOBSpeaker: Leonel Marques Antunes Ferreira (CERN) -
14:50
→
15:00
Discussion 10m
- 15:00 → 15:30