Status

  • HTTP+TPC: XRoot issue #1373 was fixed upstream and Michal was to backport to v4.12. Status?
  • Tests with CNAF using delegated X.509 credentials, see #209
  • Token authorisation configuration (not a blocker for LHCb migration)
  • LHCb DAQ tests: Maria has been testing DAQ to EOS with xrdcp (no DIRAC yet), 10 GB/s.

Schedule

  • 15 February: green light, if all tests are OK we proceed. If there are unresolved problems we can postpone. Prepare OTGs.
  • 22 February: disable write access to CASTOR LHCb in preparation for migration. Check all queues are flushed and everything is written to tape.
  • 1 March: disable CASTOR LHCb. Migrate to CTA.
  • 8 March: EOSCTA LHCb in production

To Do

  • Finish testing HTTP+TPC
  • DAQ functional test
  • Publish OTGs