(meeting in conjunction with TCom)
INTEGRATION (CERN)
Update for the Tcom on the integration activity.
RCA was finalised last Friday.
79 components integrated and 10 cancelled (for several reasons)
ACTION: CMS (currently cancelled) to be reconsidered this week after UNIBAS updates for inclusion in RCA
TESTING (4DSoft)
Savane has been updated for testing.
ACTION: 4DSoft to foresee RA by end of January (postponed 1 month), priority should be given to the CL
ACTION: 4DSoft to provide the results of the CL services tests by the first week of January to be included in the report
Next meeting tomorrow Thursday 21 at 3PM.
ACTION: CERN to organise next meeting
ACTION: CNR to distribute the draft template
There are minutes attached to this event.
Show them.