2021 gas systems projects
→
Europe/Zurich
Not-LHC experiments (NA61-ND280 and CLOUD) 05/03/2021
Present: Beatrice, Roberto, Kacper, Fabio, Patrick, Mattia
Indico: https://indico.cern.ch/event/1015274/
General
- Resources used in February reported by Beatrice: https://indico.cern.ch/event/1015274/contributions/4260788/attachments/2202463/3725622/UpdateOnPlanning_05March.pdf
- Not used resources for exhaust: to finish in week 10
Analysis module (reported by Fabio)
- Fabio reported that safety valve of 300 mbar are leaking at 220 mbar --> to use CERN one for NA61 and to check if we can use also for ND280. To send an email to company
- To check with LPh if we can use safer valves at 400 mbar โ> Fabio/Lph
Exhaust (reported by Fabio and Mattia)
- All material in workshop except MFM (ordered for NA61)
- Few mechanics done this week
Distribution (reported by Fabio and Mattia)
- Front panel to do on Wednesday with Ace โ> Andrea
- Distribution ND280: still to final drawings
- Distribution NA61: to do just after exhaust
Pump (reported by Kacper)
- Some pieces from cern store should arrive in w12: Kacper to check next week. In case material will not be there, pump construction module will be in w13 and w12 will be for CLOUD
Electrical (reported by Patrick)
- NA61: missing chassis analysis --> 13/03
- ND280: missing chassis exhaust, analysis, extension purifier --> 13/03
Cabling for March:
- 2 racks analysis
- 2 racks mixer, when they will be ready in the workshop
- ND280 rack exhaust
General and installation
- Patrick reported about the need of buying cable trays and final installation: to discuss next week also with Fred
- Patrick reported about the lack of mechanic manpower โ> to check next week
- Mattia to prepare a plan of rack with pipes
CLOUD (by LPh)
- No report
- Patrick reported about the need of buying cable trays
There are minutes attached to this event.
Show them.