GIF++ installation and schedule meeting
Remote only
CERN
-
-
11:00
→
11:05
New Announcements 5m
Commissioning of the GIF beam dump:
Proposed date: Beginning of July (just before NA physics)
We should be ready to give feedback, e.g. counting rates etc.
----------------------------------
New gas installation request for NA61 & NA64:
Proposed date: together with the annual maintenance in the week 18 (03-07.05)
Installation of a new gas patch panel for the NA64 (upstream GIF++). In principle we will need to stop the neutral gas supply for 1h in order to connect a two ways valve starting from our patch panel in the preparation area. In the meantime, also the iC4H10 line will be stopped at least for half a day. It will be needed in order to connect on the same line (bldg. 909), a new one for the NA61 experiment.
----------------------------------
Irradiator Maintenance : NO OPERATION ! LIMITED ACCESS !
Scheduled : Week 9 (01-05.03)Cancelled because of COVID-19 restriction
Fall back : Week 18 (03-07.05) - Very questionable----------------------------------
GIF pyTIMBER : Not opertional
Changes to access TIMBER (authentication required)
Retiring of access tools used. We will have to re-write the whole tool.Solution has been proposed.
We need to see if this solves the issue.----------------------------------
GIF Logbook :
Discussion started if we can move to accelerator logbook. -
11:05
→
11:15
Muon Beam Scheduling 2021 10m
Preparation and Scheduling of Muon Beam Time 2021.
Will be reviewed when we get the beam plan end of AprilWe expect to receive the first version of the NA schedule (including GIF) in end of April.
We now need to start the space planning for the beam weeks.
Please provide either a CAD drawing (preferred) or food-print (frowned upon) of your setup so we can see how / if they can be aligned along the beam line.SPS North Area p+ 12.07.2021 to 15.11.2021 (18 weeks)
Beamline Weeks Requested
H2 20 (111%)
H4 37 (206%)
H6 31 (172%)
H8 33 (183%)"Arbitration is needed for the H4 beam-line (and to a much smaller extend for the H2 beam line) between the NA experiments and the LHC test-beams."
-
11:15
→
11:30
Weekly planning 15m
WILL BE UPDATED DURING THE MEETING !!!
----------------------------------
Weekly Planning : https://teamup.com/ksvh7dak8mub8k7xpe
UPSTREAM : Default filter settings : 2.2
DOWNSTREAM : Default filter settings : 1----------------------------------
ATLAS - MM :
2 long term chambers placed (on the ceiling), operational -> exit next week
LM2 placed below long term one.
Middle chamber removed, replaced in front of CMS-CSC.
Propose to raise the chamber by ≈ 40 cm.
Proposal to stay until summer.
ATLAS - sTGC : Lot of problems with gas system. Gas keeps stopping. Roberto investigating.
New chamber arriving on Friday. Two shipments in transit.ATLAS - sMDT :
Request run 4.6 until Tues.CMS - CSC: Restarted irradiation. Gas purifier to be changed.
Stop Ar over the weekend caused problems. Chamber needs to tested and analysed.
Upstream chamber relocated. GC measurement pending.
EP-DT2 : The aging test with eco-friendly gas mixture are going well.
Request : Once per month test with Ar, operated from a local bottle.CMS-DT: Expected to return to bunker later this year. INFN still blocking activity outside Italy.
EcoGas: New detector installed. Running. Test campaign resumed using eco-friendly mixture (HFO).
Request : from 12.04 - Mo to Friday filter 6.9CMS-RPC: Radiation program resumed on trolley 1.
From now on, whenever a source OFF scan is needed, they are going to try to use the upstream abs set to 333 for most of the time. iRPC prototype chamber removed.ATLAS-RPC: Coming back for the moment, not before June 2021.
---------- -
11:30
→
11:35
New requests for tests at GIF 5m
introduction, goal of the test, plan, needs
BLM measuring campaign announced / ≈ 100 BLM, 6h approx. Week 45 (November 2nd till Friday 6th ). We will arrange everything in a way that the setup could be installed inside the bunker in the upstream area near ATL-sTGC setup -> postponed until next year
----------------------------------
Bulgaria academy of science -> testing of new type of radiation monitor systemA new setup of ALICE-RPC will come. More news in coming weeks.
Lab on Fiber (LOF) dosimeterGas recuperation system to be installed - Responsible : Roberto
4 additional racks in Gas Service area. One containing flammable gas.
FG detection system to be installed, power needs to be provided.
(DELAYED by a few months. Will be first installed in CMS, and only later come to GIF) -
11:35
→
11:40
Long Term Planning 5m
Gas usage at GIF : we need to compile a table of gas mixture / consumption
Gas training courses : ATEX level 1 and F-Gas training courses.
List of trained people to be collected.- https://lms.cern.ch/ekp/servlet/UNIVERSALSEARCH?ACTION=SEARCH&KEYW=atex
- https://lms.cern.ch/ekp/servlet/ekp?PX=N&TEACHREVIEW=N&PTX=&CID=EKP000039939&TX=FORMAT1&LANGUAGE_TAG=en&DECORATEPAGE=N
Patrol rights : Will be reset before the Muon Beam (July).
Please contact Giuseppe for re-qualification.Training Session for CESAR to be organised before beam time.
-
11:40
→
11:45
Infrastructure & Upgrades to the Facility 5m
Improvements needed or planned for the facility.
Speakers: Giuseppe Pezzullo (CERN), Martin Richard Jaekel (CERN)Monitoring of primary lines to be done. This year we will have the monitoring of the neutral gas (Ar/CO2/Helium/N2), instead next year it will be done also for the other (iC4H10, R134a, SF6, CF4 etc.). This signals will be then available in PVSS.
On going discussion for main HFO gas supply line
Removal of the fire detection interlock with the GIF++ control room. Transparent.
Ticket not closed.GIFCS-Pytimber app issue still under investigation
-
11:45
→
11:50
General Items 5m
-
IMPACTs for 2021 5m
Guidelines for filling in IMPACT requests
List of active IMPACT declarations : https://impact.cern.ch/impact/secure/activities/accessPoint/YDALC02-PPE154
General Guideline : One IMPACT per setup.
- two chambers on individual supports -> 2 IMPACT declarations
- multiple chambers swapped on same or similar support -> one IMPACT declaration
- basically, if you need two locations, please make two IMPACT declaration (clone)
Each Setup should have IMPACT label attached with number.
Attached documents : CAD file or picture.
Review working hours : if your declaration includes the bunker area, please state the number of hours you want to stay INSIDE the bunker only (for RP purposes). -
CoVid-19 5m
CoVid-19 Risk Assessment for the Facility : https://edms.cern.ch/document/2376286/1
General guideline :
- ONE setup to enter the bunker at any given time.
- All presence at the GIF and access to the bunker needs to be announced via Teamup beforehand (!)
- Traceability of people on site : Logbook ! - List all the people you encountered.
-