SPS coordination meeting
Access system card issue and single event upsets (Pierre Ninin)
SEU because of integration issues: most crates where the old ones were. BA1 integration constraint, needed to be moved to the bottom of the pit. Still checking whether BA80 SEU.
Comment by Brennan: why have the electronic card issues not be seen during the testing phase, what will be improved in the procedure? Became apparent only during full integration.
Action: Planning for re-placement of cards. Start on 9th of August. Tenatively 2 h per week. Define planning with Access experts. Start with BA1, BA80, BA1, ECN3, TAG41
NA target steering and issue of steering to T10 - lessons learned (J. Bernhard)
Issue for T10/K12 steering: 5 wrong polarities and SEMs not working.
Action: full post-mortem and how to improve check-out period and BI integration. Define improved BI in P42. Establish collaboration with SPS operation to share algorithms, techniques, tools.
Status of long. blow-up (G. Papotti)
4 test sessions carried out so far. Probably good settings for frequency band. Firmware upgrade to have program for more than only 1.5 s in cycle. More test required to see whether really OK for 4 batches. Issue also to establish 4 batches due to MKDV vacuum limitations and deconditioning.