Chair: Mike Lamont; Scientific Secretary: Malika Meddahi
-
J. Wenninger09/12/2010, 11:30The assumed LHC beam parameters for 2011 are first summarised. The overview of the 2011 schedule is presented and includes hardware commissioning, beam re-commissioning, re-validation, scrubbing, technical stops, MD, ions and special physics run requests. A proposal is made for the strategy in intensity stepping up and potential issues are described together with possible actions. Finally,...Go to contribution page
-
M. Lamont09/12/2010, 12:05A very first attempt is made to synthesis the outcomes of the workshop. A list of issues and prioritized actions will be presented. With broad brush strokes, the beam commissioning strategy for 2011 will be outlined and the requirements the different teams involved will summarized.Go to contribution page
-
S. Myers09/12/2010, 12:50