Week 48 - MCBRD IHEP Follow up meeting
Presents : Yingzhe (IHEP), G kirby, A Foussat (CERN)
Excused: A Musso, Qingjin, E Todesco, H Felice
Minutes meeting and actions item list :
- Cold Test :
- CB04, CB06 are going ot be tested on IHEP station from next week.
- CB 05 shall be tested on IMP station , possibly by 03 dec.
The outcomes of the tests shall be discussed and presented at a review, date on week 49 to be proposed.
- Production: CB08 is under wet winding curing stage.
- The production of windings beyond CB08 shall be on hold until reviews of test outcomes and technical review of open VPI process issues and QA inspection of winding impregnation with wet winding relative to last VPI CB02 findings.
- Procedure: Updated procedure of Wet winding and VPI shall be uploaded.
Actions:
- Pending : All formers manufacture, anodization and inspection reports to be uploaded in MTF.
- Updated procedures of wet winding and VPI to be uploaded following commenting.
- Date of test outcomes and VPI process reviews to be fixed
There are minutes attached to this event.