WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

Europe/Zurich
zoom (CERN)

zoom

CERN

    • 14:00 14:20
      Brazing Procedure Specification discussion 20m
      Speaker: Fritz Motschmann (CERN)
    • 14:20 14:40
      CuCD preliminary update 20m
      Speaker: Gregory Cattenoz (CERN)
    • 14:40 15:00
      Ongoing topics 20m

      MINUTE 42:

      BPS:

      • New procedure with a commonly used brazing with Ag, Cu, Pd. The behaviour is better regarding the strength et corrosion. Procedure attached to INDICO, EDMS 2739710

      Plug-in:

      • Asset creation
      • Delays are tight, lot of refusing because of the delays and quantities

      Mechanical table assembly:

      • Assembly procedure is almost finished
      • Cycling test will begin soon on 1 TCLPX and on 1 TCTPXH
      • STI have to take the CEM rack for the cycling tests

      TCC:

      • Christophe (CEM) will update the software to be easier to understand/ have values
      • Malik will work on it on the hardware part and for a potential chiller bath

      Design:

      • Washer to protect bellows during FE welding design to finish
      • Update the TCTXPV plug-ins
      • Jaw lifting tool to design
      • Jaw and tank procedure
      • Braze fitting leak test tool
      • Ears for lifting of the collimators with a slope: 19mm difference

      Absorber materials update:

      • CuCD blocks tested on bench n.6, oil machined blocks good with 2x650°C, next batch with 4 or 8 blocks in a row
      • Inermet to be sent to metrology – No updates last time

      Combitac:

      • Waiting for costs and delays
      • Check the quantities needed
      • Design modifications due to holes position

      Production:

      • Shaft on Monday from TT, then last machining step
      • Contouring tank plate ongoing
      • RF contact new drawings for the serie
      • Beam pipes done, then welding and carbon deposite
      • BPM flange at 40/30 with leak test on repaired ones
      • Cu parts 1 month left

      Additional screws:

      Graphite tapering:

      • Asked to Pablo to order 2 blocks – 2 more block only if metrology is good on the first 2 ones.
      • 2 first blocks in metrology
      • Taperings procedures to attach on MTF

      Update on planning:

      Update for the serie:

      Others:

      • Waiting for the first and last RGA tests final reports
      • Tools for flatness measurement: check the compatibility (point 4 or 132)
      • VSC needs jaw lifting tool for the tests regarding the weight of the jaws assemblies

      Link to EDMS minutes : https://edms.cern.ch/ui/#!master/navigator/document?D:100889947:100889947:approvalAndComments