WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

MINUTE 57

 

TCC:

  • Financial issues between CERN and Julabo
  • Waiting for Jean-Marc updates on soft and to get back the date from TCSPM LS2
  • PT100 connectors installed – Régis will check to order the tubes connectors 

BPM flanges:

  • 3 Flanges ok – 2 remaining
  • Test of connectors only are all good
  • Plan B : production of flanges to Ositrade in parallel

Design:

  • RF fingers:
    • Hybrid version between TCS and TCSPM: longer than TCSPM to avoid stress, additional screw to avoid stress on welding + lyre for flexibility (design TCSPM with TCS length)
  • DN300 flanges with pinch-off: waiting the CDD from VSC 
  • Jaw flatness measurement tool -> give the CDD to Dylan for the tooling list
  • TCLP, TCSPM, TCTPM folders: not started 
  • Post-proto modifications regarding Dylan’s Excel: ongoing for jaws, done for mechanical table
  • Shims for IP1 or taller feets: ongoing
  • Cover update regarding CZ5: ?
  • Switch integration: ongoing
  • TCTPXV review and modifications for serie: will be reviewed WP5.2 14th of November 
  • Mechanical table procedure: ongoing 
  • Gabarit for cooling pipes production: ongoing, wait for comments 
  • Extremity RF fingers new design (ok regarding stress to reduce length): not started 
  • Copper wedges for jaws posing during vacuum test (STI)

Jaw assembly:

  • TCLPX waiting for TCC
  • TCTPXH disassembled and blocks to Carlotta

Absorber materials update:

  • Blocks arriving mid-November then metrology and TT
  • Check ongoing by Carlotta for a tomography of the blocks 

Production MME: 

  • Tanks under control with new references
  • RF screen rail electropolished, metrology done
  • LHCTCLPX__0142 transition support ongoing
  • RF fingers production 
  • 2 references for tank missing

Production STI: 

  • Jaw flatness measurement tool: ongoing
  • Levelling parts: ongoing
  • Remaining feets components: ongoing
  • Adaptation for vireur: ongoing
  • Transitions and pinch-off: not started
  • TCC rack: done
  • Lifting ears: not started
  • Adjust length of the RF fingers testbench

Update on planning: 

  • + 3 months for TCTPXH because of Inermet production 

Update for the serie:

  • Check for a modification of the guiding plates regarding the trivial process for protos 
There are minutes attached to this event. Show them.
    • 14:00 → 14:10
      BPM flanges update 10m
      Speaker: Joel Daricou (CERN)
    • 14:10 → 14:20
      Planning update for Inermet TCTPXH jaws 10m
      Speaker: Dylan Baillard (CERN)
    • 14:20 → 14:40
      Extremity RF fingers proposal 20m
      Speaker: Luca Gentini (CERN)
    • 14:40 → 14:50
      Ongoing topics 10m
      • UHV tests for TCLPX jaws
      • Tightening tests at 5Nm on the spare Inermet blocks ?