B163 upgrade - Installation meeting

→ Europe/Zurich
Germana Riddone (CERN)
  1. repair of Cold box: problem with HX.  A new one has to be supplied ==> Olivier
  2. interference with vent line ==> Nicolas will supply the 3D models ==> Frederic to contact Christian and Florian
  3. feet of Fresca 1 ==> Frederic to verify the status and if needed take actions 
  4. installation of F2 outer cryostat: from 28/09
  5. transport of F2 inner cryostat to B163: 19/09
  6. Platform: corrections done

Fredric will organize weekly meetings with the team on Mondays morning

 