B163 upgrade - Installation meeting

→ Europe/Zurich
Germana Riddone (CERN)

Status w49

  • Scan realised in week 48 - good results (3D model will be updated accordingly) ==> ACTION Nicolas
  • Firm (TESI) for the platform will arrive next week (partial installation limited to Fresca 1)
  • Pressure test on 29.11: ok ==> CRG instrumentation can be completed
  • Cold box reconnected - test W50 ==> handover to CRG Operation
  • List of tasks MSC to be supplied to Olivier PIrotte for the planning update ==> ACTION Christian
  • Rail for the quick connect: at cern this week W49
  • Vent line: offer received Severin d' Armancourt, about 800 k, installation in January 2023
  • EN-EL intervention for the WCC cables: feb 2023
  • TE-MPE: protection tests in March 2023
  • Platform fore storage insert: feb 2023

 

upon completion of the installation, two possible options. ==> decision Jan 2023

  1. test with Fresca 1 (if Helium availability allows)
  2. commissioning of Fresca 2 (outer cryostat)

 