ADTC MEETING
YETS follow-up
Francois presented the status of the YETS activities. The switch from the big cooling water pump to the small one to limit energy consumption and reduce the noise will be performed tomorrow 17th Nov. The exact timing has to be agreed with OP and GBAR as it will impact ELENA and the experiment operation. Bertrand, Patrice and Nicolas to discuss.
The shielding opening is ongoing for the extraction of BHN46 magnet. QDW47 will be extracted too to limit the number of large concrete beams to be removed, the storage of which would be problematic.
It is reminded that ELENA will operate with Hminus till 15th Dec, so all services must be kept on in consequence.
The ECR for the extraction of ancient DEM line elements (BHZ35 and XGEM33) has been approved. This is scheduled in agreement with AEgIS for the week 3 of 2024.
It is requested to add a switch for the light in AD ring, that can be actuated from the inside of the ring.
SEM grid in LNE02 AEgIS will be swapped in January. An ARR will be produced. Compatibility of flange and readout must be ensured as this is a 1mm pitch electrode, instead of 0.5 mm now.
ALPHA control room RP survey
Claudia reported on RP measurements performed in ALPHA control room. The values measured are compatible with a continuous occupation local, although non negligible. In case of increase of luminosity inside AD, it could become a limiting factor. RP will make suggestions for possible shielding improvements.
New TELMAX project
Maud introduced the TELMAX (TEst Line for Machine And eXperiments) project, which aims at replacing the former ATRAP 2 experiment by a test beam line on the currently unused LNE03 vertical transfer line. In order to make the line as usable as possible, it will include a 90° bend, a la STEP, to bring the beam to horizontal direction. The shielding of the zone has to be completely remodeled to adapt to the new configuration and the access will be moved onto the AEgIS side gangway. RP simulations show that the residual dose in the ALPHA storage room nearby (ex-ATRAP laser room). It was therefore clarified with the experiment that it must remain a storage area and must not be converted into a permanent workplace. When the remaining ATRAP solenoid will be removed, the hole left in the floor will have to be blocked by a metallic plate, nevertheless allowing optical reference transfer for BE-GM.
It is also requested that the hand over point remain at the existing level (vacuum valve in the vertical section) and that the subsequent elements be easily extractible in order to increase versatility and adapt to test setups possibly installed vertically.
The ECR is still in approval loop, comments can still be added.
AOB:
-The lock-out procedure for ELENA ion source has to be clarified by Bertrand with Alessandra
-The access date for swapping AEgIS SEM is to be clarified
-A cable was damaged in LNE07, it may have to be replaced. If confirmed, it shall be checked if it can be done at the same time as the installation of STEP cables in ELENA zone by P. Lelong.