ADTC MEETING
Francois showed the status of the ongoing and upcoming YETS activities in AD/ELENA machines. The planning of the anticipated services disruptions was shown once again, in particular the AUG tests on 16th-17th December, the auto transfer tests on 19th December, the cryo distribution stop 6th December - 11th January, and the experiment side crane (8th January- 1st of March).
The magnets extraction operations are now complete, the shielding has been re-installed and the visit itinerary is accessible again. Survey operations were performed according to schedule.
The vacuum maintenance operations planned (BGI pump oil exchange, sublimation pump filament exchange, line 6000 pump oil exchange are either ongoing or complete.
The ELENA ion source lock out procedure needs to be clarified, Bertrand is working on it.
The LNE07 ZQNA cable that was damaged will be repaired, and it is expected that a spare cable can be pulled at the same time as the cabling campaign for STEP.
The SEM0225 in the AEgIS zone has been removed. The new one will be installed as soon as the acceptance test is complete, in principle with 2 weeks. The ARR has been prepared and will be circulated soon.
Maud showed the status of the ALPHA barrack replacement. The preparation works have been performed according to schedule, the scaffolding to access the roof is in place. The tap water pipes that are located at the back of the barrack will be removed. It is also asked that there should be a possibility to cut the tap water upstream with a valve located outside the ELENA area.
The crane cannot be used when there are people on the roof of the barrack. The procedure is that people accessing the roof must take the remote control of the crane with them. Priority is nevertheless given to crane operations for the experiments
Patrice showed the expected planning of GBAR for the YETS. The operations requiring Hminus and the LINAC will be stopped on the 14th evening. No beam on the 15th. The Hminus beam is expected to restart asap in 2024, ie around 6th of February. The pbars are not expected before 17th of April, although delays are to be expected due to DSO tests conflicts with other machines. Craning operations will be required in January, this should in principle be OK, even if the crane will be used sporadically for the other crane refurbishment operations.
Theo showed the planning of AEgIS. There is in principle no impact of the SEM 0225 swap. The DEM line elements removal is planned for mid january, the impacted AEgIS elements will be removed beforehand.