ADTC MEETING
AD YETS works follow-up
Francois showed the progress of planned works in the frame of YETS. Good progress is noted on all sides, in particular for the refurbishment of the AD ring magnets, which is going according to schedule. BTV maintenance is late, new dates being discussed with BI.
SEM grid 0225 was extracted from LNE02 (AEgIS) transfer line. A new grid will be fitted, with a 1mm pitch instead of 0.5 mm. The extracted grid will be re-installed in LNE03 (TELMAX) line, after the faulty FE boards have been reoplaced.
ELENA H-minus ions run will finish on 14th as planned.
The cryo factory is down due to heavy refurbishment works ; dewars have been delivered to BASE as expected, which will allow to bridge till early January.
The refurbishment of the experiments side crane will start as planned on 8th January. It will impact the ELENA side crane during the operations of trolleys transfers (18th-22nd January).
The AUG tests of this week-end (16-17th Dec) will affect everybody. Another power cut is planned for 19th at 6h for secure power tests. BASE request to be called just before power is cut. Demi water will be shut from Friday 18h till Monday 8h. The SCADA vacuum control system will be OFF from Friday 12h till Tuesday 12h.
ASACUSA YETS activities
Eric showed the planned ASACUSA 1 and 2 activities for this YETS. None of them involve usage of the crane. The positron source will be replaced. The values of expected consumption for GHe and LHe where shown and discussed. The table summarizing the planned consumption throughout 2024 has been communicated to David Jaillet (Gas) and Johan Bremer (liquid). It is added to the minutes of the meeting. The peak consumption is expected during summer with up to 23 dewars per week. Reaction expected from cryo team.
ALPHA YETS activities
Niels showed the planned activities for ALPHA. The ALPHA-g magnet has been re-installed after a number of cryo-heads have been replaced. Also the LHe transfer line has been replaced by a fixed one, which may result in major savings, to be validated.
The ALPHA control room refurbishment is in full swing. Recabling activities will start after all the walls have been removed. The underlying metallic structure will be checked and modelled in 3d, in order to decide if the upper floor can be installed.
AOB
James explained that a cleaning campaign will be requested from all parts. AEgIS has been targeted in this first stage. Experiments are warned that no bean permit will be signed in case the zones are considered too messy.
ASACUSA gangway RP protection being discussed. The annihilation region located just underneath is requested to be shielded, possibly with borated polyethylene.
The extraction of old DEM line elements from the AEgIS zone (XGEM33 and BHZ35) is cancelled, due to conflict with crane refurbishment and regain of interest for a possible future high energy line.