ACTION TO BE DONE:
- Dylan call Emilien when TCLPX jaws ready for untightening.
- Luca and team shall sign in C1: Interconnect, Flanges, gabarit.
- Emilien shall put a report on the indico regarding tomography.
- Romain will contact C. Garion that is used to design RF fingers for other application to get advice.
- Luca shall find the reference available on website for the TCTPXH washers.
- Carlotta will check the energy deposition to check if the extremity blocks need a good cooling (Emmanuel will send a screen of the CAD model).
- Romain will order and cut and clean and silver plating M4x35.
- Dylan and Romain will find the LHCTCTPXH_0013 missing (but not very far…).
- Dylan will send the update for the interconnection tool to Emmanuel. (Done)
- Gregory will give feedback of the PT100 vacuum test once performed (gaine under VSC cleaning this time, as for LS2).
- Emmanuel will update the gabarit to change the housing by pins to delimitate the contour, with some margin around. Only 1 drawing for X H and V, another model for TCSPM. Emmanuel will give the CDD to Dylan to add it on the Excel tool.
OTHER ACTIONS:
TCC:
- TCC preliminary test started with TCLPX.
- Several test ongoing to validate the testbench and for Luisa and Carlotta (with all the data).
BPM flanges:
- Tomography done, the welding of the connector itself is good, we cannot see the inside (ceramic) -> Difficult to give a conclusion here (check attached report).
- 4 new flanges under production to re-launch test -> A discussion with AP and STI and BI will be organized. 1 flange ongoing in machining to test welding with passive cooling with TIG. SubD9 ordered by Jerome.
RF fingers:
- Romain launch silver plating: 2x5mm, 1x10mm, 1x15mm. EBW ongoing.
- Adjust length of the RF fingers testbench.
Design:
- TCLP, TCSPM, TCTPM folders: not started
- Post-proto modifications regarding Dylan’s Excel: ongoing for jaws, done for mechanical table, almost finished for feet
- TCTPXV review and modifications for serie: Emanuel working on it
- Mechanical table procedure check: ongoing
- Gabarit for cooling pipes production and assembly: ongoing
- Copper wedges for jaws posing during vacuum test (STI)
Assembly:
- TCTPXH jaws re-assembled without blocks to do a fake insertion in the tank.
- Tank sub-components assembled.
Procurement:
- Inermet blocks production ongoing, arriving at CERN End of March
Production MME:
- Tank cover arriving mid-March (input from Emilien) then cleaning.
- Nanoker will re-machine the wrong blocks
Update on planning:
- Collimators shall be operational for July.
- TCLPX prevision: Mid-October
- TCTPXH prevision: Mid-November
- RF fingers, Inermet, BPM flanges, TCC test bench are on the critical path.
- Cooling for April
Update for the serie:
- Check to put an elastic element as TCLPX for TCTPXH and avoid overlength of the blocks.
- Define a probe cable length for serie with Jerome.
- Put sliding contact for BPM clamps.