TCTPXV review and modifications for series: Emanuel working on it.
TCLM masks: not started.
Copper wedges for jaws posing during vacuum test (STI) –> Clara adds it on the Excel list.
Production MME:
Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118 -> flanges for proto S21, mock-up S24 with metrology + cleaning -> Deadlines seems ok.
Cooling circuit: 3 received from ELI industries – No delivery date to give for the moment and job to be created (remaining steps: correction, machining, metrology, brazing, cleaning, leak test, pressure test).
RF fingers: Chemical cut of the fingers support ongoing with a 3 fingers-opening, fingers under silver plating, then EBW -> 10+5 fingers support. Emilien is using the fingers already cut.
Cap + spacers + other collars (with electropolishing + rhodium): 6th of June
2 rhodium parts available
Others rhodium parts next week
RF spacers: difficulties to machine -> 15 more days
1 short NEG Cartridge -> Finished.
BPM flanges finished; Dylan will take back the remaining connectors.
Update on planning:
Update for the serie:
There are minutes attached to this event.
Show them.