WP5.2 - TCLPX/TCTPXH Prototypes Production Follow-up

→ Europe/Zurich
zoom (CERN)

zoom

CERN

MINUTE 73:

LAST WEEK: 

  • TCTPXH pressure test ok
  • PT100 acceptance test: Good, Gregory suggests continuing with the series production (in June).
  • MME remaining parts to be produced.
  • Dylan shall prepare a procedure for PT100 + Sub-D9 cleaning. 
  • Dylan shall prepare a procedure for RF fingers production (input from Emilien).
  • Dylan shall prepare a procedure for BPM flanges production (input from Emilien).
  • Emilien shall send the BPM leak test report.
  • Hositrad flanges in June.
  • Jerome will bring Ceramtec connectors to Gregory to validate them before installation.

OTHER ACTIONS:

TCC:

  • Remi shall finish the procedure waiting for the last update from JMQ.

RF fingers:

  • Proposal of a new design for reinforcement ongoing by Romain
  • Romain is preparing a report.
  • For proto: no annealing + 5 microns silver plating.
  • Special tool for EBW welding -> Dylan adds it on the Excel list.

Design

  • TCLP, TCSPM, TCTPM folders: Ongoing. 
  • Post-proto modifications regarding Dylan’s Excel: Ongoing 95%.
  • TCTPXV review and modifications for series: Emanuel working on it.
  • TCLM masks: not started.
  • Copper wedges for jaws posing during vacuum test (STI) –> Clara adds it on the Excel list.

Production MME: 

  • Flanges to machine: 2xLHCTCLPX_T0129 + 2xLHCTCLPX_T0118 + 2xLHCTC__X_T0116 + 2xLHCTC__X_T0118 -> flanges for proto S21, mock-up S24 with metrology + cleaning -> Deadlines seems ok.
  • Cooling circuit: 3 received from ELI industries – No delivery date to give for the moment and job to be created (remaining steps: correction, machining, metrology, brazing, cleaning, leak test, pressure test).
  • RF fingers: Chemical cut of the fingers support ongoing with a 3 fingers-opening, fingers under silver plating, then EBW -> 10+5 fingers support. Emilien is using the fingers already cut. 
  • Cap + spacers + other collars (with electropolishing + rhodium): 6th of June 
    • 2 rhodium parts available
    • Others rhodium parts next week
    • RF spacers: difficulties to machine -> 15 more days
  • 1 short NEG Cartridge -> Finished. 
  • BPM flanges finished; Dylan will take back the remaining connectors.

Update on planning: 

Update for the serie: