   A focus will be addressed to the SM18 2023-Projects with high priority and upgrades involving CRG-Sections in the next months :

 

  • 25kL-Dewar reconnection and commissioning

 

  • F2-SClinK commissioning
  • F1 Shuffling module, process, implementation, commissioning
  • A2 Shuffling Module, process, implementation, commissioning
  • C2 Shuffling Module, process, implementation, commissioning
  • B2 Shuffling Module, process, implementation, commissioning
  • V6 new RF-cryostat process development and commissioning
  • CCU cold compressor process and commissioning for IT STRING Project
  • SVB + SQXL + DFHX process development for IT STRING Project
  • 6kW-LINDE-A Cold Box process adaptation to IT STRING Project operation

 

  • RF-bunkers and Cryostats : Interlocks, Alarms and Lock Out for Major Safety Aspects 

 

  • Diode process development and commissioning
  • Siegtal Process development and commissioning

 

  • Grafana KPI development and implementation for quenches recovery

 

  • HFM bypass valve for Quench recovery optimization, hardware implementation
  • CLUSTER-D bypass valve for Quench recovery optimization, hardware implementation

 

In support of discussions, I’m currently preparing a global planning for all NON-LHC activities, including SM18 Projects; with tasks & resources involved versus some operational constraints for the test benches 

 