11T Long Dipole Prototype Recovery Phase 2_Collaring test preparation

Europe/Zurich
zoom (CERN)

zoom

CERN

  • Slide 4

Point 3 about the key transition of the pole has to be checked in the future assembly and will not be seen during this test (because there is no Fuji paper on the pole).

  • Slide 10

Phase 1 of collaring: it is possible that the tool is not close at 25bar, in that case we increase to 30bar and (if it necessary) to 35 bar.

Addition step in phase 3 of collaring: once the tool is close, check if the keys can be inserted from the connection side just to have additional information.

  • Slide 14

The connection of the laser to have it "in life" during the collaring is still in process and it is not certain that we will have it during this collaring. If not, the tool displacement will be checked only with the feeler gauges.

  • Schedule

Wednesday 30/08/2023: collared coil will be placed in the tool of the press. 

Thursday 31/08/2023: Connection the acquisition system of the instrumented collars and laser.

Friday 01/09/2023: Connection the acquisition system of the instrumented collars and laser.

Monday 04/09/2023: Connection the acquisition system of the instrumented collars and laser.

Tuesday 05/09/2023: Connection the acquisition system of the instrumented collars and laser.

Wednesday 06/09/2023: COLLARING (we need one complete day).

There are minutes attached to this event. Show them.