Major Incidents Changes 1m
-
14:01
→
14:02
Summary of Operational Status and Issues 1mSpeakers: Brian Davies (Lancaster University (GB)), Darren Moore (Science and Technology Facilities Council STFC (GB)), Kieran Howlett (STFC RAL)
-
14:02
→
14:03
GGUS /RT Tickets 1m
https://tinyurl.com/T1-GGUS-Open
https://tinyurl.com/T1-GGUS-Closed -
14:04
→
14:05
Site Availability 1m
https://lcgwww.gridpp.rl.ac.uk/utils/availchart/
https://cms-site-readiness.web.cern.ch/cms-site-readiness/SiteReadiness/HTML/SiteReadinessReport.html#T1_UK_RAL
http://hammercloud.cern.ch/hc/app/atlas/siteoverview/?site=RAL-LCG2&startTime=2020-01-29&endTime=2020-02-06&templateType=isGolden
-
14:05
→
14:06
Experiment Operational Issues 1m
-
14:15
→
14:16
VO Liaison CMS 1mSpeaker: Katy Ellis (Science and Technology Facilities Council STFC (GB))
(Writing on Tuesday morning, 10th Oct)
Failing SAM tests last week on Monday - Thursday inclusive, as well as Saturday. On Wed and Thur, this was due to the squids having been taken down (relating to the CVMFS-not-updating issue). The rest of the time it was the usual insufficient gateways problem. I prevented CMS from going into drain during the week, as jobs were performing well. On Sunday morning we went into drain again, but I left it as it was, since the job pressure in the global system was low anyway.
Concerning the CVMFS-not-updating, this affected CMS Tier-0 Processing jobs. These are new types of jobs, that previously only ran at Tier-0, but now also run at Tier 1s. I believe they do prompt processing. They needed the very latest version of CMSSW so were unable to run at RAL until CVMFS was fixed.
At time of writing, CMS job pressure is improving, but we are not back to the usual number of running cores worldwide.
-
14:16
→
14:17
VO-Liaison ATLAS 1mSpeakers: James William Walder (Science and Technology Facilities Council STFC (GB)), Jyoti Prakash Biswal (Rutherford Appleton Laboratory)
- GGUS-163297:
- RAL-LCG2: deletion errors; in progress.
- RAL-LCG2-ECHO_DATADISK is back to be below its threshold (the dashed lines; the plot is also attached). Let's wait and watch for a few more days.
- Ticket was updated yesterday.
- Grid is draining again today - presumably due to lack of tasks.
- RAL saw a reduction in jobs around 06:00 hrs.
- The RAL CVMFS issue and the fix have been discussed in most of the meetings this week.
- RAL-LCG2 and RAL-LCG2_ECHO continue with scheduled downtime (04 Oct-01 Nov).
- Host intentionally disconnected during network reconfiguration.
- GGUS-163297:
-
14:20
→
14:21
VO Liaison LHCb 1mSpeaker: Alexander Rogovskiy (Rutherford Appleton Laboratory)
-
14:25
→
14:28
VO Liaison LSST 3mSpeaker: Timothy John Noble (Science and Technology Facilities Council STFC (GB))
-
14:30
→
14:31
VO Liaison Others 1m
-
14:31
→
14:32
AOB 1m
-
14:32
→
14:33
Any other Business 1mSpeakers: Brian Davies (Lancaster University (GB)), Darren Moore (Science and Technology Facilities Council STFC (GB))
-
14:00
→
14:01