EN-ACE-OSS and HL-PO planning meeting - Meeting for deinstallation forward physics at Point 1

Europe/Zurich
Zoom Meeting ID
63196521362
Host
Michele Modena
Alternative host
Paolo Fessia
Useful links
Join via phone
Zoom URL

 

Meeting on: 8/12/23 – Deinstallation of Forward Physic experiments at IP1

Invited: Marko Milovanovic Marko.Milovanovic@cern.ch; Maciej Trzebinski maciej.trzebinski@cern.ch; Ludovico Pontecorvo ludovico.pontecorvo@cern.ch; Martin Aleksa Martin.Aleksa@cern.ch; Marco Ciapetti Marco.Ciapetti@cern.ch; Francisco Sanchez Galan francisco.sanchez.galan@cern.ch; Francesca Paola Nicoletti francesca.paola.nicoletti@cern.ch; Paolo Fessia Paolo.Fessia@cern.ch; Marzia Bernardini marzia.bernardini@cern.ch; Estrella Vergara Fernandez estrella.vergara.fernandez@cern.ch Eric Page Eric.Page@cern.ch; Giuseppe Bregliozzi Giuseppe.Bregliozzi@cern.ch; Maria Barberan Marin maria.barberan.marin@cern.ch

 

Minutes:

 

Here are very brief Minutes of our Meeting, mainly as a follow-up list of actions:

 

  • Ludo/Marco: Cables in UPS galleries (air core cables) will remain (to be cut at the red door level) à ACTION Gianluca to contact AFP team to see the concrete possibility of saving those cable parts and to establish a plan for that work of cable saving
  • Cables in the LHC Tunnel will be de-installed
  • Francisco/ Gianluca: will organize meetings targeting the de-cabling à ACTION
  • Francisco: he proposes to have a visit on site in January for the future de-cabling aspects toward USC55 à ACTION
  • De-cabling is to be prepared/supervised with Gianluca but done by the EN-EL contractor. This scenario will be confirmed when the cost is known (under evaluation)
  • ZDC crane will be de-installed AFTER the transport out of the TAN (in March 2026)
  •  

ALFA stations (between Q6-Q7 so out of the HL nominal area):

  • S1-2: already de-installed
  • S8-1: could be taken out on the next YETS (EYETS 24-25) , so before LS3. Eric agrees with this
  • à ACTION: Estrella to integrate this in LS3 Planning
  • Re-cabling (Marco): to be tackled on March 24 after convergence of Gianluca on cables trays layout integration à ACTION

 

 

Michele Modena , HL-LHC Project Office; CERN, ATS-DO - CH-1211 Geneve 23, Switzerland;
Phone +41 22 767 3469|

There are minutes attached to this event. Show them.
    • 16:00 17:30
      Round table discussion 1h 30m
      Speakers: Estrella Vergara Fernandez (CERN), Henri De Maynard (Unknown), Maria Barberan Marin (CERN), Marzia Bernardini (CERN), Michele Modena (CERN), Paolo Fessia (CERN)