ERAM Meeting

Europe/Zurich
Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
    • 11:00 11:45
      ERAM status
      Conveners: Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
      • 11:00
        ERAM production status at Rui's lab 5m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
      • 11:05
        Mesh pulsing 10m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
      • 11:15
        ERAM gluing 5m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)
        • ERAM46 and 47 flued last week
        • ERAM-48 is the last one to glue

        fabrication drawings to update and validate in their last version (for future possible use) --> Saclay BE (Fabrizio)

         

        2 stiffeners remaining (at Saclay)

        ask cern metrology for groove 

      • 11:20
        ERAM testing 10m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura Munteanu (CERN), Laura-Iuliana Munteanu (CERN)
        • ERAM-42 scan

         

        • ERAM-46 scan planned this week

         

        remaining : ERAM-47-48 and redo ERAM-39 (was scanned with fec 7,10 same cards as ERAM-40)

      • 11:30
        ERAM AOB 15m
        Speakers: Alain Delbart (Université Paris-Saclay (FR)), Charlotte Riccio (CEA-Saclay (FR)), David Henaff (CEA), Guillaume Eurin (CEA/IRFU/DPhP), Laura-Iuliana Munteanu (CERN)

        Status of detectors (update/corrected)

        • 16 ERAMs on bot TPC + ERAM-12 (large RC) and 35 (200 kOhm) as spares (at JPARC)

         

        • Global Status of ERAMs production for TOP TPC

        ERAM-07 : pb seen when bot TPC assembly (not short circuit but too much dust and mesh hole ! )

        ERAM-11 : mounted on bot TPC !

        ERAM-14 : mounted on second test box in large clean room. to me removed and staored

        ERAM-15 : mounting pb on bot TPC --> checked OK at saclay --> usable. at Saclay

        ERAM-16 : cc repaired

        ERAM-20 : large gain in border

        ERAM-27 : THE "surplisingly good" one from bad batch 25-34

        ERAM-36 small spreading issues

        ERAM-37 small spreading issues

        ERAM-39

        ERAM-40

        ERAM-41

        ERAM-43

        ERAM-44

        ERAM-45

        ERAM-38

        ERAM-42 (to be confirmed after scan this week) glued on new stiffener

        • ERAMs considered "last choices" for TOP TPC

        MM1-DLC2 (ERAM-00 in database)

        MM1-DLC1

        ERAM-25 : bad batch, gain gradient : cards reused

        ERAM-33 : bad batch, gain gradient : cards reused

        ERAM-34 : bad batch, gain gradient : cards reused

         

        ERAM-18 : RC/2

         

        • first selection of "first choice" ERAMs for TOP TPC : 15 ERAMs + 3 (ERAM-46-48)

        ERAM-14

        ERAM-15 : mounting pb on bot TPC --> checked OK at saclay --> usable

        ERAM-16 : cc repaired

        ERAM-20 : large gain in border

        ERAM-27 : THE "surplisingly good" one from bad batch 25-34

        ERAM-36 small spreading issues

        ERAM-37 small spreading issues

        ERAM-39

        ERAM-40

        ERAM-41

        ERAM-43

        ERAM-44

        ERAM-45

        ERAM-38

        ERAM-42 tsvan to be confirmed, glued on new stiffener)

        • remaining ERAMs = 3 ERAMs

        to glue

        ERAM-48

         

        to scan

        ERAM-46-48 with cards 1,5,6,11 and 15 - 76 (from ERAM-33)

         

        ERAM-39 or 40 to rescan with cards 80 and 84 (from ERAM-27) (they both use cards 7,10 !)

         

        • Status of FEC cards available at CERN

        remaining to be used

         

        1, 5, 6, 11  (blue cabinet) + reused 15, 76 to scan ERAM-46 47 48

         

        73 the only one to rescan ERAM-39 or 40 which were scanned with cards 7, 10. a c ard is missing to rescan this eram.

         

        missing card : 44 

        card 73 alone ? with fec 37 which was damaged and repaired .... originally affected to ERAM-12

        to check : the 4 cards at Tokai which should have been  the ones affected to ERAM-15 and 12 (54, 37) and (44, 24)

        BUT 24 and 37 are at bdg 182 ! 44 and 54 are missing. And the 4 FEC cards at JPARC are 14,72, 30, 35 !

         

        link to the FEC database (oct 30 update)

         

        https://docs.google.com/spreadsheets/d/1iRTUKPFwUWPPxpArdMIPp6gJQ4hf5w8jEh1RlN5_dRQ/edit#gid=1720131687

         

        Alain checked all the pieces needed for TOP TPC

         

        • short of 2 copper serpentins. 2 "bad" ones were  recovered (labelled #1 and #3) ... labelled #2 can not (Didier proposed to built a new one). The 3 were qualified for water leaks