TMD:
- Send the team the proposed schedule.
- Continue with the tooling development. Jigs and graphite plate.
- Measure the last try to confirm no deformation on the laterals.
COMEB:
- Continue working on the box production with the objective of sending it before the end of the month.
- Upload the design of the box when finished to the server.
VDL: Keep an eye on the next production forecast to start in March (TBC)
CERN:
- Cross-check the last metrology of the cells for the test and the metrology from TMDs try 3.
Gerardo:
- Start circulating the task report to every participant.