Francois presented the status of the YETS planned activities. The experiment side crane refurbishment is going on as planned. The other crane is blocked today and tomorrow for transfer of the new chariot. The ALPHA barrack replacement is stopped, waiting for the crane to be back in operation, to allow to install the new barrack as of 1st February. VSC cabling planned in the ring is delayed till next year due to late availability of the cabling team.
QFN32 magnet refurbishment will finish 1 week earlier, so it will be taken back to AD on Monday 22nd, hence a rescheduling for the re-installation in the ring. All teams have been informed and can adapt to the new schedule.
BHN46 will also be a few days early, causing the visits on ELENA platform to be interrupted on 24th instead of 27th January.The early arrival of BHN46 may be a good news for the restart schedule, TBC.
ELENA activities are coming to an end. RF cavity amplifier was replaced as planned. The ion source maintenance is complete, and back under vacuum. The installation of SEM 0225 (AEgIS) is planned for 19th January. No TDR test can be performed on it due to unavailability of the tool. SEM 0338 installation is delayed till 12th of February. The cabling for STEP started late but will be finished before end of W3, so that un-lock-out can take place as planned on 22nd and DSO tests can be scheduled on 24th January. IST's for septum should be pushed back by 1 day to avoid possible conflicts with DSO tests. HW tests by EPC can start as soon as the machine in un-locked out. Start of commissioning with ions planned on 12th of February may start a bit earlier, depending on the time needed for the demineralized water cooling system maintenance (could be limited to 2 days instead of 5, TBC). The operation with Hminus may be somewhat interrupted for installing the SEM 0338 and the subsequent long pumping required. GBAR will be informed.
The electrical substation is currently undergoing a complete refurbishment, hence it is asked to limit the power consumption till mid-February (fits with AD shut down). ELENA not expected to impact a lot.

 

Davide showed a draft version of the slides that will be displayed in Chamonix WS. The topic is to check what will be needed to operate the AD/ELENA complex for another 10 to 20 years. He reminded the facility challenges, in particular caused by aging HW, but also the lHe demand exceeding capacity of the cryo plant, and space constraints that limit the number of experiments and the surface they can occupy. Although present users do not require changes in  the beam characteristics in the short and medium term, we are anticipating on future needs and requests that may arise for our world-wide unique facility. The review of items that would need to be consolidated/improved was quicly shown, with a timeline compatible with an operation till 2042. New possibilities for the future were introduced for potential more fancy physics (anti neutrons, anti deuterons, exa quarks etc), and possible significant improvements of the facility like the expansion into another new building -existing or to be built. Davide asked all people concerned to check the slides shown and give feedback in case of wrong numbers or wrong interpretation.

 

AOB: GBAR LINAC beam permit signed