- Upstream the merging point: items move but possibly supports can be re-used. From the merging point onwards, beamline height is different: old supports cannot be re-used.
- MME: BI contacts MME for instrument AND support
- We need to put everything in PLAN and then to contact MME and EN EL
- MBG.412022 is the first magnet that does not move. Downstream of that, things move.
- Spectrometer room will not be needed most probably.
- After 2nd plasma cell we have the same beamline height.
- Discussion with Vittorio needed for the 50 mm aperture of 150 MeV line.
- Survey / alignment / integration will be part of Ans workpackage. They will need to check that existing instruments are compatible with their alignment tools
- To be agreed what kind of budget code shall be used for new and existing supports