Attending: Paz Alonso Arias (PAA), Matteo Volpi (MV), Riccardo Boldrini (RB), Ping Wang (PW), ZAib Un Nisa (ZN), Carmello Barbagallo (CB)
Melbox. MV has continued with the calibration of the line. Found in HPDC difference inn 0.5dB with respect to measures done at CERN.
Loads now at 4kW, never seen that power before. Bead pull meas. ready, but nothing to test. 3D printing one sample structure to test.
Spectrometer contract ready now, and ready for shipment. PAA confirms Sergio has been preparing docs for shipment
Xboxes. Xbox2 running flat at 80MV/m without further problems (*) Xbox3 HEK calorimetry campaign has started, but some problems with accuracy (maybe due to flow readings)/
(*) After meeting, Walter has come to suggest to try to go up now. PAA and RB will change target settings.