HI-ECN3 target complex service building design - 911 new door
Present: Fernando, Nikola, Eva, Tamara, Kincso, Rachid, JL
Similar door size (7mx4m) to forsee some adjustment could be envisaged (reduction of the overal height and width for exemple not not touch the cable tray bellow the crane rails)
List of actions
Different groups (CV, EL, HE, AA, IT, SCE) to investigate services installed on the wall of the 911, propose alternative location, identify possible impact, dependencies, duration of the work and costs, activities forseen within NA-CONS
Francois, Richard, JL: Investigation if door optimization is possible in view of the dismantling of the current experiment (max size of biggest object) and if this will not impact he installation of the new experiment taking the assumption of large experiment componnents will be lowered via the new shaft and target complex
SCE (Kincso, Tamara) to perform a preliminray assesment of the new door to indentify possible showstoppers
Identification of fire, ventilation and safety requirements for the new door Melania, Oriol?
A contact for IT-CS need to be identified (relocation of network socket and Wi-Fi
Follow-up meeting after Easter vacation