CLIC Project Meeting #2
→
Europe/Zurich
60/6-015 - Room Georges Charpak (Room F) (CERN)
Steinar Stapnes
(CERN)
-
- 09:00 → 09:45
- 09:45 → 10:00
- 10:05 → 10:40
-
10:40
→
12:40
RF structures and test-facilities
-
10:40
Structure programme and the need for test facilities 15mRF structure test-programme. Critically review the capabilities to produce the number and variety of structures proposed, identify follow up points Introduce about the test capacity needed: Covering KEK-SLAC, "traditional" X-band facilities at CERN and other collaborators, multitube systems at CERN and outside CERN introduce, justify the needsSpeaker: Walter Wuensch (CERN)
-
11:05
Coffee Break 25m
-
11:35
Experiences with and status of the X-band testing facility at CERN 15m- Experiences with current klystron and options ahead - CPI order and purchase options - Plans for 2-3 such systems at CERN Followed by a discussion including collaborators that could aim to install such systemsSpeaker: Gerard McMonagle (CERN)
- 12:15
-
10:40
- 12:45 → 13:00