CRU meeting revival kickup

→ Europe/Zurich

Present: Olivier, Julien, Marian, PiPPo, Marco, Ola, Gudda, Erno

MAIN GOAL

  • ITS3 and FOCAL readout using CRU + lpGBT during RUN 4 (starting in 2029)
  • support for existing detectors using CRU

MILESTONES (2024/2025)

  • ITS3 Feb 2025 readout and configuration of MOSAIX chip using CRU.
  • FOCAL test beam in 2025 using CRU

 

We miss more details on the required feature for these tests beam. We should also link the hardware requirements of these 2 new detectors in the CRU documentation so it is easy for all the experts to retrieve information

WORKING MODE

  • periodic meeting with all the firmware experts, we will start seriously ater summer
  • GITLAB to merge detector code contribution from different experts
  • GITLAB issue tracking (no JIRA ticket)
  • Setting up CI for test and simple simulation
  • DOCUMENT of firmware in MARKDOWN directly on the GITLAB repo

CONTRIBUTIONs

OLIVIER

responsible for the CRU firmware

PiPPo

Interface as O2/detector expert. Firmware contribution to be discussed

OLA

Part of ITS3 readout package (WP6) will contribute to the project the first 6 months

JULIEN

Firmware contribution in CRU and porting the firmware to FELIX card

GUDDA

Part of the ITS3 readout work package (WP6), contribution to the ITS3 UL,  followi the test of the MOSAIX chip and integration of blocks re-usable in the UL of the CRU

MARCO

Brazil is involved in the FOCAL firmware development. Colleague from Brazil could not participate to the meeting

ERNO

Contirbution to the CRU firmware, lpGBT and FOCAL UL.

MARIAN

Interface to the trigger system, contribution to larger simulation model CRU<-> LTU. CTP emulator

CI

  • We will set up CI using vunit+nvc (faster than gHDL)
  • proposal to extend the CI to build the FPGA binary files. RIVIERA tool could be used as simulation program to test specific IP CORE

 

NEXT PLAN OF WORK

  • set up the next meeting
  • prepare small tutorial on how we discuss between colleagues and compile the project in the current CRU system
  • start to assing task to different experts
  • set up mattermost channel and add new people to the alice-cru-core mailing list (this contains strictly people involved in the development of the firmware ... no general discussion

NOTE

During the RUN3 activities a lot of components have been developed for different detectors. Before implementing specific component for the 2 new detectors we should be sure it is not implemented already.

When modifying common part it is very important to keep the compatibitility with the current system, the CRU will remain active for the whole RUN4 period and used by the majority of the detectors.

There are minutes attached to this event. Show them.
    • 10:00 → 10:25
      Introduction 25m

      Known upgrades required for RUN4

      Speakers: Filippo Costa (CERN), Olivier Bourrion (Centre National de la Recherche Scientifique (FR))
    • 10:25 → 11:00
      Discussion 35m