HL-LHC BGI - project status (round table) - CANCELLED

Europe/Zurich
zoom or 864/2-B14 (CERN)

zoom or 864/2-B14

CERN

Gunn Khatri (CERN), James Storey (CERN), Miguel Navarro Baeza (CERN), Paolo Fessia (CERN)
    • 1
      Status of the project

      Gunn and James will say a few words on where we are in terms of progress. If there are any changes in the objectives and milestones for the EYETS 24-25 and LS3

      Speakers: Gunn Khatri (CERN), James Storey (CERN)
    • 2
      Instrument design, vacuum and alignment
      Speakers: Chiara Pasquino (CERN), Maria Teresa Ramos Garcia (CERN), William Andreazza (CERN)
    • 3
      Magnet design
      Speaker: Dominique Bodart (CERN)
    • 4
      Power converters
      Speakers: Gilles Le Godec (CERN), Yves Thurel (CERN)
    • 5
      Cooling water
      • for magnets and instrument, split from existing circuits
      • for power converters (Polaris 2P), will be NEW cooling circuit
      Speakers: Alexandre Pierre Marion (CERN), Olivier Crespo-Lopez (CERN)
    • 6
      Racks, cabling and optical fibers
      • existing empty racks from SY have been identified for BGI use
      • pre-DIC submitted for cabling (RQF2586206 and RQF2586205 )
      • DIF submitted for fibers (RQF2583352)
      • 40 kV DC signal cable not a CERN standard, any solutions found ?
      Speakers: Georgi Minchev Georgiev (CERN), Ioanna Ioannidi, Jose Gascon (CERN), Julien Charles H Emonds-Alt (CERN)
    • 7
      DAQ, control and electronics
      Speaker: Mark Mclean (CERN)
    • 8
      ECR for EYETS 24-25
      Speakers: Gunn Khatri (CERN), James Storey (CERN), João Oliveira (CERN)
    • 9
      AOB