TMD:
Furnace fixing ongoing, final test to be performed by the end of this week 31.
CF flanges machining and preparation on going.
We decide to look for an alternative furnace (plan B) in case the reparation is no longer an option.
Prepare the material that is needed for testing that the furnace is finally operative again. SS + copper brazing + pollution test.
COMEB:
Green light for sending the machined WG to CERN for measurement.
VDL:
Machining on going.
CERN:
Check the method on how the nickel is coating the WR90