Presents : A. Beynel, Z. Arenas, E. Grenier, I. Zarei, A. Boucherie, S. Marzari, J. Vollaire (partially)
- the topographic measurements of the hill after the construction will be done, it's already done the actual shape on top of the hill (V. Sanchez)
- during earth removal, zoning with stakes is nessessary layer after layer to define limit of the activated earth area (V. Sanchez february 2026)
- it will be necessary to scan the position of the 2 Helium tanks with connected pipes and valves attached to it (during next yets 2024-25)
- it will be necessary to scan the buildings, boris tubes etc... after the earth and dumps removal (april 2026)
- For scans the contact person is Alban Vieille BE/GM/ASG
- an alignment check after the works will be done for the 2 Frontends GPS and HRS (october 2027)
- if possible the alignment of the Robot rails into the Target area 838 will be monitored during the wortks on top of the roof (during 2026)
- The chimical fixation of the rails has to be assesed due to the recived level of radiations
- An internal scan will be done after the new building construction (May 2027)
- 2 temporary holes will be useful to check coincidence between Target area and Separator area alignment systems (october 2027)
- Before the shielding installation, it will be necessary to trace references on the internal floor / walls to help the "calepinage" (june 2027)