Draft:
Present: Gunn, Alex
-
new turbo+controller ordered by A. SInturel (will arrive in January 2025)
-
new gauges+controller ordered by Gunn (ordered from CERN store, should be here in days)
-
need to order a CF40 cross, two CF40 to CF16 zero length adaptors, a CF 16 TEE, a CF 40 to KF40 adaptor, a CF16 to KF 16 adapter and a few helicoflex seals in KF16 and KF40
-
Verify on the cryostat design on KF connection size
-
Alex noticed that we used EVAC ISO seals with Helicoflex seals, and some KF rubber O-rings, so this is a bricolage, new connection will unify and make all metal connections.
-
need to make cable installation request to EN-EL by 18 Oct (do we already have some spare cables coming from the rack AYH6-06 near RF stuff into the ring section15?
@Jocelyn Tan)
-
Discuss with Mark on how to setup electronics (PLC, 24 V and relay) for the Pump-speed to Valve control.
-
Get gate valve connector (Amphenol type)
There are minutes attached to this event.
Show them.