PASTE meeting

→ Europe/Zurich
Andrei Tsaregorodtsev
Description
CERN, bat 2 R-030 To join the telephone conference, click here: https://audioconf.cern.ch/call/0122882 To dial in to the conference: a. Dial +41 22 7676000 b. Enter access code 0122882
Production and PASTE Meeting, 22nd May 2007, CERN Chair: A.Tsaregorodtsev Minutes: S. Paterson CERN: M.Bargiotti, G.Castellani, P.Charpentier, J.Closier, A.Smith, S.Paterson, R.Santinelli Phone: R.Bernet, R.Graciani, U.Marconi, R.Nandakumar, M.Sapunov, A.Tsaregorodtsev Apologies: N.Brook 1. Production Status Report Minutes from the production meeting are available here. Joel reported that no MC simulation was running, new workflows are being constructed that will use the latest Gauss release ( ACTION: Joel ). The reconstruction activity was affected last week by VOMS related issues (see the production minutes for more information). This has now been resolved and the reconstruction is running at 5 Tier-1 sites. Philippe raised the issue of root protocol at CERN and confirmed that the issues relating to inconsistent TURLs have been resolved. Stuart agreed to put this in place pending tests at CERN, PIC and CNAF (which previously were problematic). Rather than lcg-getturls, it was agreed to continue using lcg-gt directly and later make use of the python binding to GFAL when this becomes available ( ACTION: Stuart ). The problem with runit creating detached python processes was observed again, this time with the Agent Director. This confirms Andrei's suspicion that it is related to external commands which are not properly cleaned. The possibility of using an Agent in the WMS to monitor running processes and clean up as required was discussed. Joel mentioned that PIC seemed to be back in production after the tape robot malfunctions but no update had been sent, Ricardo agreed to investigate ( ACTION: Ricardo ) Roberto enquired about the GFAL plugin to root and Philippe gave a summary of the status. Two different backend SEs (DPM and Castor) have the same interface but are incompatible (libshift). The GFAL plugin for Root is currently under development. Since the possibility of using a DPM SE at NIKHEF exists, Philippe agreed to investigate the protocols currently supported by Root and if it is possible to have an application accessing Castor and DPM files in a consistent way ( ACTION: Philippe ). Philippe also reported on UI deployment through the AA. Oliver Keeble has deployed native SLC4 32bit versions of the lcg-utils, GFAL and LFC client (including CMT requirements). This should simplify the certification procedure. 2. Production Operations Issues There was some discussion of whether LHCb should provide separately packaged versions of Root for user jobs. It was agreed to pursue making versions of Root available through install_project.py ( ACTION: Hubert ). Stuart agreed to contact the Ganga developers to discuss the implications for their Root handler. ( ACTION: Stuart ) Marianne gave a summary of the DC06 cleanup status. LFC support have been contacted about the first large deletion of files, the ticket was opened on the 25th April and Marianne is waiting for a response. The DST removal from the LFC has started and is expected to take between 1 and 2 days. Site admins can then be contacted and Marianne is preparing the lists for this. Stuart mentioned that user analysis jobs are suffering from the old SE naming conventions (e.g. CERN_Castor) where data is failing to enter the Stager. Marianne agreed to start cleaning these entries. The fixes to incorrect SA paths are now underway, Marianne confirmed that the Castor SURLs are now corrected. Roberto agreed to escalate the issue of SRM SAM tests (e.g. srm-get-metadata with timeout) being added to site critical tests. ( ACTION: Roberto ) It was decided that timing information from the Stager should be viewed as a separate picture and not included in the SAM tests. In addition to the site metadata information, the time required to stage files should also be reported ( ACTION: Stuart, Andrew ). For the LHCb SAM tests, an srm-get-metadata with a timeout of 120s was agreed to be reasonable. This can be part of the current SAM test and could also include a DaVinci job to test file access from the WNs ( ACTION: Joel ) 3. DIRAC3 Tasks Andrei attached a summary of the DIRAC3 workshop to the agenda (link here). The current plan is to have another session at the end of June. In order to test the DIRAC3 deployment mechanism, volhcb03 can be installed from scratch. Andrei confirmed that more WMS services are in the pipeline. Andrew raised the issue of pyOpenSSL on Windows, Ying has compiled this in the past and will be contacted for more information. Andrei mentioned that Gianluca had prepared a discussion summary of the job prioritization which was also circulated to Philippe and Nick. Comments will be sent from Andrei as soon as possible. ( ACTION: Andrei ) 4. AOB The issue of a VOMS group for VO Support was discussed and Joel agreed to set this up. GGUS is not VOMS aware, however, this should simplify the management of the list (ACTION: Joel).
There are minutes attached to this event. Show them.
    • 10:00 → 10:15
      Production status report 15m
      - Report from the Production meeting:
    • 10:15 → 10:45
      Production operations issues 30m
      - User proxy with LFC - DC'06 clean-up status - SAM SRM critical test
    • 10:45 → 11:15
      DIRAC3 tasks 30m
      - Summary of the last week development session - Current tasks
      Slides
    • 11:15 → 11:25
      AOB 10m
      VOMS group for the LHCb user supporters