Anna: need to identify readers at institutes immediately, need also to get dates for comments from them
Eirik will follow up at UiO
Therese made an appointment with HVL people to look over it (9th)
Therese: will work on the impact but will need help from NTNU and UiA on the industrial side
Therese: good idea for someone to do the merging of the Excellence
James and Eirik will do it
Eirik/James will follow up on the computing side, with help from Matthias &c
James: what is the difference between implementation and organisation/structure?
Various answers given but not really clear
Therese: need to allocate someone for the implementation
Eirik: start a new tex file in the overleaf for the implementation —> Anna will do it
Eirik: everyone should look and add things that are missing
James: are these two things less important than the rest?
Anna: no, probably just as important, but might be possible for it to be a bit later
Anna: discussed the organisation part before writing it
Ali: slide 14 from the presentation to industry with the three layers (the diagram) could also be used in the Excellence.
Eirik: will try to fit it into the Excellence
Budget: may need letters of support from (e.g.) NorCC when funding of people would change if the centre were to be funded. Will differ from institute to institute. Need to understand what the internal deadlines are.
Heidi: no overlap is allowed
Ali: what does staff mean? WP leaders or what? Co-supervisors?
Therese: put in all names, not just those directly funded by the centre. If you’re co-supervising a student in the centre this is a contribution-in-kind
Eirik: if a name goes in the table does it go in the budget
Heidi: yes
Are CVs needed for everyone in the table?
15 CVs maximum.
Summary
James/Eirik will do the Excellence with Are
Therese: Impact
Anna: Implementation
James/Eirik: computing
Budget: NTNU (Are ++)
Table of person power (Therese)
Svein: confusion about WP6. Hope to clarify this in a meeting next week.
Are: similar table would be useful from the other institutions.