Minutes D2 weekly meeting, 25/11/2024
- SF decided to put on hold the last 3 apertures manufacture of MBRD, those involving the largest coil pairing until the cold test results of LMBRD1
- MBRD03 yoking is complete, magnetic measurement being performed. Expected delivery form second end Jan 2025
- The week, all other D2 activities are put in hold so for ASG personnel to concentrate on Falcon D preparation of winding trials
- SF asks for a meeting with MSC and SMT management to discuss with INFN the issue at ASG of coactivity of D2 manufacture and FalconD and more importantly the important need of training oa young engineer on winding tack for Falcon D project.