·         Presentation of the new Technical room localisation on top of the access gallery

·         The room 25m2 is too small, Stefano present 2 variants for increasing it to 35m2

·         For Fabio version 1 or 2 are RP point of view more or less similar, in case we can add some shielding out of the 738 , after the meeting, Fabio ask if it's possible to increase it in direction of Geneva instead ?

o    => to be checked with SCE Martin

·         Concerning the new requests, EL needs to know the additional power we need for :

o    Vacuum Racks (action Abel)

o    Air cooling unit (action Nina)

o    Telecom (Marc-Antoine)

·         In all cases, we must foresee enough scabbards to be able to pass new cablings in future, it's already planed in the IRP

·         Marc-Antoine et Jose prefers to have Racks IT star point and Telecom adjacent:   

·         Marc-Antoine needs "réseau secouru" for Telecom

·         Marc-Antoine needs to know the additional cost of room extension (action Martin)

·         Guillaume accepts to share the RP rack with Christophe M. in case the connection to 197 building is too difficult, to be discussed (action Stefano)

·         Verify the size of the EL cabinet in function of the new requests (action Patrick)

·         Nina needs a reservation outside for the heat exchanger, she will send the dimensions (action Nina)

·        

·         Fabio advice to have the feedthrough towards the ground gallery as far as possible to the beam axle

·        

·         Stefano ask each stakeholder to check fill the table with pertinent information, especially the number or IT connections needed for each rack / cabinet (action all)

Best regards, Stefano and Antoine

 

New meeting 21.02.2025 with SCE: M.Manfredi, G.Cnudde, J.Dauge, and STI: AP.Bernardes, F.Pozzi and Stefano

  • presentation by Stefano 2 variants of increasing the Technical room to 35 m2
  • Variant 1: discarded !
  • Variant 2: st1A09019_01
  • after discussion the Variant 2 is choosed by SCE
  • SCE will do the modification of the building with Variant 2 and reservations for electrical feedthroughs (action Johan)
  • ask EN-HE if the yellow rack is monoblock for handling (action Stefano)
  • increase the room high to 2800mm and door to 2300mm (action Johan)
  • Three layers of cable trays will pass into the acess gallery 736
  • ask Didier Chabuis (access) if end zone door ground level can be also the access door (action Stefano)

 

Kind regards, Stefano 

 