911 new doors -On-site visit with EN-ACE, SCE and Integration

Europe/Zurich

Meeting 02/04/2025: Creation of the new lorry and personnel door 

  • ECR: EDMS3173295
  • SCE drawings: attached (responsible: Guillaume)
  • CATIA reference:  ST1906031_01 (responsible: Bea)
  • Dimensions of SCE aren’t the same as the ones in the BE-EA integration model
    • New measurements were taken on site and the SCE measurements were accepted.
    • [Action Bea]: incorporate the agreed measurements into the model
  • The outside road is on a slope meaning that on the left part of the door there will be a 30cm difference with respect to the floor inside the building.
    • During the last CE meeting it was agreed that a  provisional material will be placed there until the new road is going to be installed
    • EN-ACE team mentioned that this solution has to be studied with EN-HE (not present in the meeting) because of the carrying of the door when installation.
    • [Action Guillaume]: create a detail of the proposed solution by SCE and ask for EN-HE validation of the proposed solution.
  • Colour of the door: it should be the same as the rest of the doors in the NA.
    • [Action Guillaume]: Check the planned colour for the doors of the rest of the buildings.
  • Control pannels:
    • The personnel door will have the badge access box in the outside
    • The lorry door will have the control box in the inside 911. More precisely, it was agreed that it will be located in the wall of the old lorry door.
    • [Action Bea]: Integrate the position of the boxes
  • Foundations for the door:
    • The doors will be installed attaching the frames to the wall from the ourside.
    • To avoid the installation of metallic plates, bellow the pillars of the lorry door, CE will add concrete supports.
    • [Action Guillaume]: Add this to the final study of the SCE works.
    • Like in this picture:
  • Caniveau:
    • As the road has a slope, there will be a water collection slab next to the door.
    • [Action Guillaume]: Add it to the CE study.
  • Personnel door:
    • It doesn’t have to be a fire door
    • The height was agreed to be 2100mm instead of 2000 that was integrated
    • [Action Yannick]: send the model of the door to Bea and Guillaume to have the final drawings.
    • [Action Bea and Guillaume]: Ones they get the model from Yannick, to incorporate it.

  • Lorry door:
    • Dimensions are agreed to be the ones in the ECR.
    • The opening of SCE will be the dimensions of the access area. The door installed by EN-ACE will be 5cm bigger in each side to clad it to the wall of the building.
    • [Action Nicolas]: To share the model with Bea and Guillaume.
    • [Action Bea and Guillaume]: Ones they get the model from Yannick, to incorporate it.
  • Schedule:
    • In 2 weeks time (for week ): SCE will have the new detail drawings (with the drainage and the access slope) for EN-HE validation.
    • Installation of the door middle of July. (They need 8 weeks from the signing with the company)
There are minutes attached to this event. Show them.