    • 1
      General news
      The first shared period would be from Monday, 07.07, until Wednesday, 16.07, for a total of 10 days. To benefit from starting on Monday, we would need to use the crane already on Friday before. 
       
      The last beam time could be from Wednesday 12.11. to Monday 24.11. with 12 days.
       
      With this adjustment in first and last period, we hope that it is possible to shift the schedule a bit to open up a period around CW36.
      Like this the second shared period could be potentially between EP FTS and LHCB ECAL in September. Of course we would prefer Wed to Wed and optimally 14days. 
    • 2
    • 3
      Muon Beam 2025

      Beam time preparation and schedule

    • 4
      New requests for tests at GIF

      introduction, goal of the test, plan, needs

    • 5
      Long Term Planning
    • 6
      Infrastructure & Upgrades to the Facility

      Improvements needed or planned for the facility.

      Speakers: Giuseppe Pezzullo (CERN), Martin R. Jaekel (CERN)
    • 7
      General Items
      • a) IMPACTs for 2025

        Guidelines for filling in IMPACT requests

    • 8
      AOCB