  • N. Peray and M. Canale: Almost finished with the drawings for winding and reaction tooling (without RHT guiding system and “sarcofage”)
    • They will transfer a first set of these drawings to the main workshop for initiating the process of searching for procurement options
    • Drawings corrections will be done in parallel
  • M. Canale is thus starting to work in the mechanical structure. We gave all inputs in terms of dimensions. Engineering design details will come in the following weeks.
  • N. Peray is starting to work in the impregnation tooling

 

  • For the mechanical structure, we set a weekly meeting (each Tuesday) to follow the activity. We will then just update on the main advancements in the general BOND meeting.

 

  • N. Bourcey also suggested to create now a detailed list of drawings with correct names and Excel file for project follow-up (before it is too late)