GENERAL UPDATE:
- Request for Cu-cable: 800 m included in SCD planning. We will try to have it by end of May / beginning June
- We also have 200 m of Nb3Sn RMC-QXF cable availalbe in 927. Note that each BOND mock-up uses 15 m. We could use some of this cable for our tests.
WINDING TESTS - PLANNING (TOOLING):
The list of action items for the next weeks is listed here:
- Create a program for the winding test
- Modify winding clamps and get ready for a new winding test
- Pole study - Design a campaign of tests to study the optimum distance in between the hard-way bend exit and the beginning of the soft-way
- Layer jump study - Think / design a two layer mock-up of the head geometry including layer jump
WINDING TESTS - PLANNING (TESTS):
The list of action items for the next weeks is listed here:
- Winding test with 2-3 turns using the program and the new clamps mentioned above. Create a small report
- Winding tests for the pole study mentioned above. Create a small report
- Winding tests for the layer jump study mentioned above. Create a small report
There are minutes attached to this event.