Summary:
- contact Vacuum colleagues to advice them the possibility to move some pipes into the separator HRS during LS3 - action Stefano
- Integrate the 6 pipes A--> B poured in the concrete slab in the civil engineering market, even if not in IRP DS - Action Martin
- check if building 738 water drains can be connected to normal wastewater network - action Martin and Fabio
- the tank for potential contaminated water under the target area will be open on top but if necessary (evaporation) we can install a light cover
- the tank capacity will be of 250 L (1 complete dump leak is 110 L) - the tank has to be easily accessible from the floor hatch
- the tank pump and piping will not be permanent, they will be installed just in case of necessity
- the dry drain installed in East Area TA8 will be adapted for our needs on top of the tank - action Stefano, Nina
- study the interface between the dump enclosure bottom and the water drain pipe - action Ida, Aleksander, Edouard
- define number and diameter of EL pipes reservation - action Stefano
- dump ventilation if needed (condensation) : organize a dedicated meeting with Edouard, Ida, Aleksander and Fabio - action Stefano
- additional irradiation point: to be discuss between us and Marco in 12.8.25 meeting
- RP validation for the corings (for survey, feed through...) - action Claudio and Stefano for 3D